37. Network Rail must repay to MSCC all costs, charges and expenses reasonably and properly incurred by MSCC—
(a)in constructing any protective work under the provisions of paragraph 28(3)(a) including, in respect of any permanent protective work, a capitalised sum representing the cost of maintaining and renewing those works;
(b)in respect of the employment of any inspectors, watchguards and other persons whom it is reasonably necessary to appoint for inspecting, watching and lighting any part of the River affected by any specified work or protective work and for preventing as far as may be practicable all interference, obstruction, danger or accident arising from the construction, maintenance, renewal, repair or failure of the specified work or any protective work;
(c)in respect of the approval by MSCC of plans submitted by Network Rail and the supervision by MSCC of any specified work or any protective work; and
(d)in bringing the specified work or any protective work to the notice of users of the River.