xmlns:atom="http://www.w3.org/2005/Atom"
10.—(1) For the purposes of section 58 of the Act, the Environment Agency must not consider a complete CCS system to be ready for use unless it has first received from the operator a notification (“a CCS notification”) in respect of the system.
(2) A CCS notification must state—
(a)each generating unit within the relevant fossil fuel plant to which the complete CCS system relates;
(b)the installed generating capacity of all the generating units stated under sub-paragraph (a); and
(c)the date on which the operator wishes the complete CCS system to be considered ready for use.
(3) A CCS notification must be submitted in such form and manner as the Environment Agency may reasonably require.