Building or StructureMaximum height (metres above 211 metres AOD)Minimum height (metres above 211 metres AOD)Maximum length (metres)Minimum length (metres)Maximum width (metres)Minimum width (metres)
Each gas turbine generator (where one gas turbine generator is constructed) (part of numbered work 2A)19.0-50.0-40.0-
Each gas turbine generator (where two gas turbine generators are constructed) (part of numbered work 2A)19.030.030.0
Each gas turbine generator (where three, four or five gas turbine generators are constructed) (part of numbered work 2A)10.036.023.0
Each exhaust gas emission flue stack (where one gas turbine generator is constructed) (part of numbered work 2A)35.030.0

11.0 (up to and includi-ng a height of 16.5 metres above 211 metres AOD) and

10.0 (from a height of 16.5 metres above 211 metres AOD to a height of 35.0 metres above 211 metres AOD)

Each exhaust gas emission flue stack (where two, three, four or five gas turbine generators are constructed) (part of numbered work 2A)35.030.010.0
Control room/office/workshop (part of numbered work 2B)6.029.023.0
Natural gas receiving station (part of numbered work 2B)5.0-50.0-36.0-
Gas treatment compound (part of numbered work 2B)5.0-29.0-16.0-
Each black start diesel generator (part of numbered work 2B)5.017.05.0
External fin fan cooler (where one gas turbine generator is constructed) (part of numbered work 2B)6.013.010.0
Switchyard/b-anking compound (part of numbered work 2C)11.360.060.0
Switchgear building (part of numbered work 2C)11.321.015.0
Gatehouse (part of numbered work 2E)4.59.08.0
Demineralis-ed water tank (part of numbered work 2E)16.023.023.0
Raw/fire water tank (part of numbered work 2E)18.015.015.0
Bat mitigation structure (part of numbered work 2E)6.010.05.0