Search Legislation

The Simple Pressure Vessels (Safety) Regulations 2016

Changes over time for: Paragraph 15

 Help about opening options

Alternative versions:

Status:

Point in time view as at 31/12/2020. There are multiple versions of this provision on screen. These apply to different geographical extents. Help about Status

Close

Status

You are viewing this legislation item as it stood at a particular point in time. At this point in time multiple versions of this provision exist for differing geographical extents. Sometimes the text of a provision is changed, but the change(s) only apply to a particular geographical area. In some limited cases where this happens, the editorial team create a version for each different geographical area. Multiple versions are only created in this way where the change in question is a substitution so that there are different versions of the text for the different extents.

Changes to legislation:

There are currently no known outstanding effects for the The Simple Pressure Vessels (Safety) Regulations 2016, Paragraph 15. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

ManufacturingE+W+S

This section has no associated Explanatory Memorandum

15.—(1) The manufacturer must take all measures necessary so that the manufacturing process and its monitoring ensure conformity of the manufactured vessels with the type described in the [F1Type] examination certificate and with the applicable requirements of these Regulations.

(2) Before commencing manufacture, the manufacturer must provide [F2an approved] body of his choice with all necessary information, and in particular—

(a)the technical documentation referred to in paragraph 2(2)(c), together with —

(i)the certificates relating to the suitable qualification of the welding operations and of the welders or welding operators;

(ii)the inspection slip for the materials used in the manufacture of parts and components contributing to the strength of the vessel; and

(iii)a report on the examination and tests performed;

(b)the [F1Type] examination certificate;

(c)a document describing the manufacturing processes and all of the predetermined systematic measures taken to ensure conformity of the vessels with the type described in the [F1Type] examination certificate, which document must include—

(i)a description of the means of manufacture and checking appropriate to the construction of the vessels;

(ii)an inspection document describing the appropriate examinations and tests to be carried out during manufacture, together with the procedures in respect thereof and the frequency with which they are to be performed;

(iii)an undertaking to carry out the examinations and tests in accordance with the inspection document and to ensure that a hydrostatic test or, subject to the agreement of the relevant authorities, a pneumatic test is carried out on each vessel manufactured at a test pressure equal to 1.5 times the design pressure; and

(iv)the addresses of the places of manufacture and storage and the date on which manufacture is to commence.

(3) The examinations and tests referred to in paragraph 15(2)(c)(iii) must be—

(i)carried out under the responsibility of qualified staff who are independent of production personnel; and

(ii)the subject of a report.

(4) The [F3approved] body must, before the date on which any manufacture begins, examine the documents referred to in paragraphs 15(2)(a) and (c) in order to certify their conformity with the [F1Type] examination certificate.

Extent Information

E1This version of this provision extends to England and Wales and Scotland only; a separate version has been created for Northern Ireland only

Textual Amendments

ManufacturingN.I.

15.—(1) The manufacturer must take all measures necessary so that the manufacturing process and its monitoring ensure conformity of the manufactured vessels with the type described in the EU-type examination certificate and with the applicable requirements of these Regulations.

(2) Before commencing manufacture, the manufacturer must provide a notified body of his choice with all necessary information, and in particular—

(a)the technical documentation referred to in paragraph 2(2)(c), together with —

(i)the certificates relating to the suitable qualification of the welding operations and of the welders or welding operators;

(ii)the inspection slip for the materials used in the manufacture of parts and components contributing to the strength of the vessel; and

(iii)a report on the examination and tests performed;

(b)the EU-type examination certificate;

(c)a document describing the manufacturing processes and all of the predetermined systematic measures taken to ensure conformity of the vessels with the type described in the EU-type examination certificate, which document must include—

(i)a description of the means of manufacture and checking appropriate to the construction of the vessels;

(ii)an inspection document describing the appropriate examinations and tests to be carried out during manufacture, together with the procedures in respect thereof and the frequency with which they are to be performed;

(iii)an undertaking to carry out the examinations and tests in accordance with the inspection document and to ensure that a hydrostatic test or, subject to the agreement of the relevant authorities, a pneumatic test is carried out on each vessel manufactured at a test pressure equal to 1.5 times the design pressure; and

(iv)the addresses of the places of manufacture and storage and the date on which manufacture is to commence.

(3) The examinations and tests referred to in paragraph 15(2)(c)(iii) must be—

(i)carried out under the responsibility of qualified staff who are independent of production personnel; and

(ii)the subject of a report.

(4) The notified body must, before the date on which any manufacture begins, examine the documents referred to in paragraphs 15(2)(a) and (c) in order to certify their conformity with the EU-type examination certificate.

Extent Information

E2This version of this provision extends to Northern Ireland only; a separate version has been created for England and Wales and Scotland only

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources