SCHEDULE 6Operational obligations of F1 notifiedF1approved bodies
1
2
3
4
5
Where a notified body finds that essential health and safety requirements or corresponding harmonised standards or other technical specifications have not been met by an installer or a manufacturer, it must require the installer or the manufacturer to take appropriate corrective measures and must not issue a certificate of conformity or an approval decision.
6
Where, in the course of the monitoring of conformity following the issue of a certificate or an approval decision, a notified body finds that a lift or safety component for lifts is no longer in conformity with the essential health and safety requirements, it must require the installer or the manufacturer to take appropriate corrective measures and must suspend or withdraw the certificate of conformity or approval decision (if necessary).
E27
Where F3 the approved body has required an installer or a manufacturer to take corrective measures and the installer or the manufacturer has failed to take such measures, or those measures have not had the required effect, F3 the approved body must restrict, suspend or withdraw any certificate of conformity or approval decision.
E67
Where the notified body has required an installer or a manufacturer to take corrective measures and the installer or the manufacturer has failed to take such measures, or those measures have not had the required effect, the notified body must restrict, suspend or withdraw any certificate of conformity or approval decision.
8
Paragraph 9 applies where a notified body is minded to—
a
refuse to issue a certificate of conformity or approval decision; or
b
restrict, suspend or withdraw a certificate of conformity or approval decision.
E49
Where this paragraph applies, F4the approved body must—
a
give the person applying for the certificate or approval decision, or the person to whom the certificate or approval decision was given, a notice in writing giving reasons and specifying the date on which the refusal, restriction, suspension or withdrawal is intended to take effect;
b
give the person applying for the certificate or approval decision, or the person to whom the certificate or approval decision was given, an opportunity to make representations within a reasonable period from the date of the notice; and
c
take account of any such representations before taking its decision.
E89
Where this paragraph applies, the notified body must—
a
give the person applying for the certificate or approval decision, or the person to whom the certificate or approval decision was given, a notice in writing giving reasons and specifying the date on which the refusal, restriction, suspension or withdrawal is intended to take effect;
b
give the person applying for the certificate or approval decision, or the person to whom the certificate or approval decision was given, an opportunity to make representations within a reasonable period from the date of the notice; and
c
take account of any such representations before taking its decision.
10
a
any refusal, restriction, suspension or withdrawal of a certificate of conformity or approval decision;
b
any circumstances affecting the scope of, or conditions for, notification under regulation 52 (notification);
c
any request for information which it has received from an enforcing authority regarding conformity assessment activities; and
d
on request, conformity assessment activities performed within the scope of its notification under regulation 52 and any other activity performed, including cross-border activities and subcontracting.
11
F2A notifiedF2An approved body must make provision in its contracts with its clients enabling such clients to appeal against a decision—
a
to refuse to issue a certificate of conformity or approval decision; or
b
to restrict, suspend or withdraw a certificate of conformity or approval decision.
E712
F2An approved body must provide other bodies F5approved by the Secretary of State carrying out similar conformity assessment activities covering the same type of lifts or the same safety components for lifts with relevant information on issues relating to negative and, on request, positive conformity assessment results.
E312
A notified body must provide other bodies notified under the Directive carrying out similar conformity assessment activities covering the same type of lifts or the same safety components for lifts with relevant information on issues relating to negative and, on request, positive conformity assessment results.
E113
E513
A notified body must participate in the work of the Coordination Group of Notified Bodies for Lifts established under the Directive, directly or by means of its designated representatives.
Word in Sch. 6 heading substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 22 para. 43(a) (with Sch. 22 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)