Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
21.—(1) The regulator may transfer to a proposed transferee an environmental permit or any part of an environmental permit—
(a)if the operator is one individual (A) and the regulator is satisfied that A cannot be found, on the application of the proposed transferee only,
(b)if the operator is two or more individuals (A and B) and the regulator is satisfied that A cannot be found, on the joint application of B and the proposed transferee, or
(c)otherwise, on the joint application of the operator and the proposed transferee.
(2) Part 1 of Schedule 5 applies in relation to an application for the transfer of an environmental permit in whole or in part.
(3) Paragraph (1) does not apply to an environmental permit (or any part of a permit) that authorises the carrying on of a stand-alone water discharge activity, stand-alone groundwater activity or a stand-alone flood risk activity.
(4) The regulator may transfer to a proposed transferee an environmental permit to which paragraph (1) does not apply, or any part of that permit—
(a)if the operator is one individual (A) and the regulator is satisfied that A cannot be found, on the notification of the proposed transferee only,
(b)unless sub-paragraph (c) applies, if the operator is two or more individuals (A and B) and the regulator is satisfied that A cannot be found, on the joint notification of B and the proposed transferee,
(c)if the operator is two or more individuals (A and B) and the proposed transferee is two or more individuals (B and C), where B is both an operator and a proposed transferee—
(i)on the joint notification of A and C, or
(ii)if the regulator is satisfied that A cannot be found, on the notification of C only, or
(d)otherwise, on the joint notification of the operator and the proposed transferee.
(5) A notification must—
(a)be made on the form provided by the regulator,
(b)include such information as is specified on the form, and
(c)specify a date on which the transfer is to take place, which must be not less than 20 working days after the date on which the notification is given.
(6) A transfer following a notification takes effect on the date specified in the notification.
(7) In the case of a partial transfer following a notification, the regulator must grant a new environmental permit to the transferee subject to the same conditions as the original permit, varied in consequence of the partial transfer.
(8) If—
(a)an enforcement notice or a suspension notice is in force in respect of an environmental permit, and
(b)the permit is transferred to another person, either in whole or in part,
the duty to comply with the enforcement notice or, as the case may be, the suspension notice is also transferred to the other person to the extent that it relates to the permit or part transferred.
(9) Unless a proposed transferee makes a joint application or gives a joint notification, the regulator may not transfer to the proposed transferee an environmental permit or any part of an environmental permit in respect of a regulated facility that ceased to be in operation more than 6 months before the proposed date of transfer.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: