Search Legislation

The Environmental Permitting (England and Wales) Regulations 2016

Changes over time for: SCHEDULE 24

 Help about opening options

Alternative versions:

Status:

Point in time view as at 31/12/2020.

Changes to legislation:

There are currently no known outstanding effects for the The Environmental Permitting (England and Wales) Regulations 2016, SCHEDULE 24. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Regulation 35(1)

SCHEDULE 24E+WEfficiency in heating and cooling energy: Energy Efficiency Directive

This schedule has no associated Explanatory Memorandum

InterpretationE+W

1.—(1) In this Schedule—

cogeneration” means the simultaneous generation in one process of thermal energy and electrical or mechanical energy;

connection distance” means—

(a)

in the case of a hot water link, the thermal capacity in kilowatts of the source or demand, whichever is smaller, multiplied by 0.0038, or

(b)

in the case of a steam heat link, the thermal capacity in kilowatts of the source or demand, whichever is smaller, multiplied by 0.0012,

expressed in kilometres;

cost-benefit analysis” means a cost-benefit analysis in accordance with Part 2 to Annex IX to the Energy Efficiency Directive;

economically justified demand” means demand that does not exceed the needs for heating or cooling and which would otherwise be satisfied at market conditions by energy generation processes other than cogeneration;

high-efficiency cogeneration” means cogeneration meeting the criteria laid down in Annex II to the Energy Efficiency Directive;

installation” means—

(a)

a stationary technical unit where one or more activities listed in Part 2 of Schedule 1 are carried on, F1...

(b)

a small waste incineration plant[F2; or

(c)

a medium combustion plant];

relevant installation” means an installation carrying on—

(a)

an activity described in Part A(1) of Section 1.1 of Part 2 of Schedule 1,

(b)

an activity described in Part A(1) of Section 5.1 of Part 2 of Schedule 1,

(c)

an activity described in paragraph (a) of Part B of Section 1.1 of Part 2 of Schedule 1, F3...

(d)

a small waste incineration plant operation[F4; or

(e)

a medium combustion plant operation];

substantially refurbished” means, subject to sub-paragraph (2)(e), a refurbishment the cost of which exceeds 50% of the investment cost for a new comparable energy plant.

(2) For the purposes of this Schedule—

(a)the definition of “offshore platform” in paragraph 3 of Part A(1) of Section 1.1 of Part 2 of Schedule 1 also includes any structure where the principal purpose of the use of the structure is the establishment of the existence of petroleum or the appraisal of its characteristics, quality or quantity or the extent of any reservoir in which it occurs,

(b)the definition of “petroleum” in paragraph 4 of Part A(1) of Section 1.1 of Part 2 of Schedule 1 also includes coal or bituminous shales or other stratified deposits from which oil can be extracted by destructive distillation,

(c)a reference to an installation means an installation which has a net rated thermal input exceeding 20 megawatts,

(d)where two or more small waste incineration plants falling within Schedule 13 with an aggregate net thermal input exceeding 20 megawatts are operated on the same site by the same operator, those small waste incineration plants must be treated as a single installation with a rated thermal input exceeding 20 megawatts, and

(e)refurbishment does not include the fitting of equipment to carry out the activity described in Part A(1) of Section 6.10 of Part 2 of Schedule 1.

Electricity generating installationsE+W

2.—(1) An application for the grant of an environmental permit under regulation 13(1) for a relevant installation which generates electricity must contain a cost-benefit analysis which assesses the cost and benefits of providing for the operation of the installation as a high-efficiency cogeneration installation.

(2) The regulator must exercise its relevant functions to ensure that an application for a variation of an environmental permit under regulation 20(1) is made before the energy plant of a relevant installation which generates electricity is substantially refurbished.

(3) The regulator must ensure that an application for a variation of an environmental permit required by sub-paragraph (2) contains (in addition to the information required by paragraph 2(1)(b) of Schedule 5) a cost-benefit analysis which assesses the cost and benefits of converting the relevant installation to high-efficiency cogeneration.

(4) The requirement for a cost-benefit analysis in sub-paragraph (1) or (3) does not apply to peak load and back-up electricity generating relevant installations for which the application for the grant or a variation of an environmental permit states that operation under 1,500 operating hours per year as a rolling average over a period of 5 years is planned.

(5) In the case of a relevant installation to which sub-paragraph (4) applies, the regulator must ensure that, if an environmental permit is granted or varied, it includes conditions ensuring that the operating hours for the installation remain within that constraint.

Installations generating waste heatE+W

3.—(1) An application for the grant of an environmental permit under regulation 13(1) for an installation generating waste heat at a useful temperature level, other than a relevant installation falling within paragraph 2(1), must contain a cost-benefit analysis.

(2) The regulator must exercise its relevant functions to ensure that an application for a variation of an environmental permit under regulation 20(1) is made before the energy plant of an installation generating waste heat at a useful temperature level, other than a relevant installation falling within paragraph 2(2), is substantially refurbished.

(3) The regulator must ensure that an application for a variation of an environmental permit under sub-paragraph (2) contains (in addition to the information required by paragraph 2(1)(b) of Schedule 5) a cost-benefit analysis.

(4) The cost-benefit analysis required by sub-paragraphs (1) and (3) must include an assessment of the cost and benefits of—

(a)utilising the waste heat to satisfy economically justified demand, including through cogeneration, and

(b)the connection of that installation to a district heating and cooling network.

Heating and cooling networksE+W

4.—(1) An application for the grant of an environmental permit under regulation 13(1) for a relevant installation which forms part of a new district heating and cooling network or existing district heating or cooling network, must contain a cost-benefit analysis.

(2) The regulator must exercise its relevant functions to ensure that an application for a variation of an environmental permit under regulation 20(1) is made before the energy plant of a relevant installation which forms part of a district heating and cooling network is substantially refurbished.

(3) An application for the variation of an environmental permit required by sub-paragraph (2) must contain (in addition to the information required by paragraph 2(1)(b) of Schedule 5) a cost-benefit analysis.

(4) The cost-benefit analysis required by sub-paragraphs (1) and (3) must include an assessment of the cost and benefits of utilising the waste heat from nearby installations.

ThresholdsE+W

5.  Paragraphs 3 and 4 do not apply to an installation, except an installation which forms part of a district cooling network, with any of the following—

(a)available waste heat of 100 kilowatts or less;

(b)available waste heat—

(i)greater than 100 kilowatts as hot water or steam, where there is no hot water heat demand greater than 100 kilowatts within the search radius from the installation as set out in the table below, and located within the connection distance from the centre of the installation, or

(ii)greater than 500 kilowatts as steam where there is no steam-based heat demand greater than 500 kilowatts and no hot water heat demand greater than 100 kilowatts within the search radius from the centre of the source installation as set out in the table below, and located within the connection distance from the centre of the source installation;

(c)a heat demand of—

(i)100 kilowatts or less for a hot water heat demand, or

(ii)500 kilowatts or less for a steam-based heat demand;

(d)a hot water heat demand greater than 100 kilowatts, with no source of available waste heat greater than 100 kilowatts within the search radius from the centre of the demand installation as set out in the table below, and located within the connection distance from the centre of the demand installation;

(e)a steam-based heat demand greater than 500 kilowatts, with no source of steam-based waste heat greater than 500 kilowatts within the search radius from the centre of the installation as set out in the table below, and located within the connection distance from the centre of the demand installation.

Search radius

Installation typeThermal capacity of heat source/demandSearch radius (kilometres), measured from the centre of the installation
Hot water demand>100 kilowatts and <3.9 megawatts0.0038 x H, where H = thermal capacity in kilowatts
≥ 3.9 megawatts15
Steam demand>500 kilowatts and <12.5 megawatts0.0012 x H, where H = thermal capacity in kilowatts
≥ 12.5 megawatts15
Waste heat source (hot water or steam)>100 kilowatts and <3.9 megawatts0.0038 x H, where H = thermal capacity in kilowatts
≥ 3.9 megawatts15

Determination of applicationsE+W

6.—(1) When considering an application for an environmental permit, or for a variation of an environmental permit, in accordance with this Schedule, the regulator must take into account—

(a)the outcome of the cost-benefit analysis carried out in accordance with this Schedule, and

(b)the outcome of any comprehensive assessment carried out in accordance with [F5regulation 4(2)(a) of the Energy Efficiency (Encouragement, Assessment and Information) Regulations 2014].

(2) Subject to sub-paragraph (4), where a cost-benefit analysis carried out in accordance with paragraphs 2(1), 2(3) and 3(4) shows that benefits exceed costs, the regulator must ensure that any environmental permit that is granted or varied includes appropriate conditions that will ensure the operation of the installation in a manner shown by that analysis to be cost beneficial.

(3) Subject to sub-paragraph (4), where a cost-benefit analysis carried out in accordance with paragraph 4(4) shows that benefits exceed costs, the regulator must ensure that any environmental permit that is granted or varied contains appropriate conditions that will ensure the operation of the installation, in conjunction with the utilisation of the waste heat from nearby installations, in a manner shown by that analysis to be cost beneficial.

(4) Where the cost-benefit analysis carried out in accordance with paragraph 2(1), 2(3), 3(4) or 4(4) shows that benefits exceed costs, the requirement to impose appropriate conditions in accordance with sub-paragraphs (2) and (3) does not apply if, in individual cases, the regulator decides that there are imperative reasons of law, ownership or finance for them not to apply.

(5) The regulator must within 2 months of its decision under sub-paragraph (4) submit a reasoned notification of that decision to the appropriate authority.

(6) This Schedule does not apply to—

(a)installations that need to be located close to a geological storage site approved under [F6Chapter 3 of Part 1 of the Energy Act 2008 and other EU-derived domestic legislation which transposed Directive 2009/31/EC on the geological storage of carbon dioxide in relation to England and Wales];

(b)any relevant installation within a nuclear site, within the meaning given in paragraph 1 of Part 2 of Schedule 23, and which is dedicated to the production of nuclear power;

(c)mobile plant.

(7) Nothing in this Schedule affects the application of the Industrial Emissions Directive to installations.

Aggregation of rated thermal input – existing installationsE+W

7.—(1) This paragraph applies to a Part B installation that is a regulated facility solely as a result of the aggregation of the net rated thermal input of two or more appliances in accordance with paragraph 2 of Part B of Section 1.1 of Part 2 of Schedule 1.

(2) A Part B installation that was in operation immediately prior to 21st March 2015 is taken to be an exempt facility for the purposes of regulation 8(2).

(3) Sub-paragraph (2) ceases to apply to a Part B installation (so that it is no longer taken to be an exempt facility) if, after 21st March 2015, the energy plant of the Part B installation is substantially refurbished.

Existing applications for the grant or variation of an environmental permitE+W

8.—(1) This Schedule does not apply to an existing application.

(2) In sub-paragraph (1), “existing application” mean a duly made application received by the regulator prior to 21st March 2015—

(a)for the grant of an environmental permit pursuant to regulation 13, or

(b)for the variation of an environmental permit pursuant to regulation 20(1).

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources