Search Legislation

The Environmental Permitting (England and Wales) Regulations 2016

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: SCHEDULE 25A

 Help about opening options

Alternative versions:

Status:

Point in time view as at 18/07/2023.

Changes to legislation:

There are currently no known outstanding effects for the The Environmental Permitting (England and Wales) Regulations 2016, SCHEDULE 25A. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Regulation 35(1)

[F1SCHEDULE 25AE+WMedium Combustion Plants: Medium Combustion Plant Directive

This schedule has no associated Explanatory Memorandum

PART 1E+WGeneral

ApplicationE+W

1.  This Schedule applies—

(a)in relation to every new medium combustion plant from 20th December 2018,

(b)in relation to every existing medium combustion plant from the date specified in regulation 12(1A)(b) or (c), as appropriate.

InterpretationE+W

2.(1) In this Schedule—

“existing medium combustion plant” means a medium combustion plant—

(a)

put into operation before 20th December 2018, or

(b)

for which an environmental permit was granted before 19th December 2017, provided that the plant is put into operation no later than 20th December 2018;

“the MCPD” means the Medium Combustion Plant Directive;

“medium combustion plant” means a combustion plant with a rated thermal input equal to or greater than 1 megawatt but less than 50 megawatts, and any combination of combustion plants referred to in article 2(2) or article 4 of the MCPD, provided that—

(a)

it does not fall within Article 2(3) or (4) of the MCPD,

(b)

it is not installed on an offshore platform situated on, above or below those parts of the sea adjacent to England and Wales from the low water mark to the seaward baseline of the United Kingdom territorial sea,

(c)

it is not installed on a gas storage or unloading platform as defined in regulation 2 of the Offshore Combustion Installations (Pollution Prevention and Control) Regulations 2013;

“new medium combustion plant” means a medium combustion plant which is not an existing medium combustion plant.

(2) In sub-paragraph (1), “offshore platform” means any fixed or floating structure which—

(a)is used for the purposes of or in connection with the production of petroleum, and

(b)in the case of a floating structure, is maintained on a station during the course of production,

but does not include any structure where the principal purpose of the use of the structure is the establishment of the existence of petroleum or the appraisal of its characteristics, quality or quantity or the extent of any reservoir in which it occurs.

(3) In sub-paragraph (2), “petroleum” includes any mineral oil or relative hydrocarbon and natural gas existing in its natural condition in strata but does not include coal or bituminous shales or other stratified deposits from which oil can be extracted by destructive distillation.

F2(4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Applications for the grant of an environmental permitE+W

3.(1) The regulator must ensure that every application for the grant of an environmental permit—

(a)includes the information specified in Annex I to the MCPD;

(b)specifies which (if any) of paragraphs 7 to 11 of this Schedule is considered relevant to the application.

(2) Subject to sub-paragraph (3), the regulator must start the procedure for determining an application for the grant of an environmental permit within one month of the operator providing the information referred to in paragraph (1) and must inform the operator of the start of the procedure.

(3) Sub-paragraph (2) applies only when the operator has submitted a duly made application.

Exercise of relevant functionE+W

4.(1) The regulator must exercise its relevant functions so as to ensure compliance with the following provisions of the MCPD—

(a)Article 4;

(b)Article 5(1) and (2);

(c)Article 5(6);

(d)Article 6(1);

(e)Article 6(2);

(f)Article 6(7);

(g)Article 6(13);

(h)Article 7 (except Article 7(8));

(i)Article 8(2) and (3);

(j)Article 9.

(2) In exercising its relevant functions, the regulator must ensure that there is no persistent emission of dark smoke, where “dark smoke” has the meaning given in section 3(1) of the Clean Air Act 1993.

(3) In exercising its relevant functions so as to ensure compliance with Article 6(1), (2), (7) or (13) of the MCPD, the regulator must ensure that environmental permits include emission limit values set in accordance with the provisions of Part 2 of this Schedule.

PART 2E+WEmission Limit Values

Interpretation of this PartE+W

5.  In this Part—

F3. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

“Annex I” means Annex I of the MCPD;

“Annex II” means Annex II of the MCPD;

“biomass”, “dust”, “emission limit value”, “micro isolated system”, “nitrogen oxides”, “operating hours”, [F4and] “small isolated system” F5... have the respective meanings given in article 3 of the MCPD;

any reference to emissions expressed in mg/Nm3 is to those emissions defined in accordance with the first paragraph of Annex II.

Emission limit valuesE+W

6.(1) Sub-paragraphs (2) to (4) apply, subject to paragraphs 7 to 11.

(2) From 20th December 2018, emission limit values applicable to a new medium combustion plant, for emissions into the air of sulphur dioxide, nitrogen oxides and dust, are the corresponding emission limit values set out in Part 2 of Annex II (but with the modification that footnote (3) in Table 2 of that Part is to be read as if for “may be” there were substituted “are”).

(3) From 1st January 2025, emission limit values applicable to an existing medium combustion plant with a rated thermal input greater than 5 megawatts, for emissions into the air of sulphur dioxide, nitrogen oxides and dust, are the corresponding emission limit values set out in Tables 2 and 3 of Part 1 of Annex II.

(4) From 1st January 2030, emission limit values applicable to an existing medium combustion plant with a rated thermal input of less than or equal to 5 megawatts, for emissions into the air of sulphur dioxide, nitrogen oxides and dust, are the corresponding emission limit values set out in Tables 1 and 3 of Part 1 of Annex II.

Limited operating hours – existing medium combustion plantsE+W

7.(1) An existing medium combustion plant which operates for no more than 500 operating hours per year, as a rolling average over a period of five years, is not required to comply with the emission limit values set out in Tables 1, 2, and 3 of Part 1 of Annex II, provided that the operator has signed a declaration in accordance with paragraph 7 of Annex I.

(2) An existing medium combustion plant is not required to comply with the emission limit values set out in Tables 1, 2, and 3 of Part 1 of Annex II where it operates for no more than 1,000 operating hours per year, as a rolling average over a period of five years to—

(a)provide backup power production in islands connected to an electricity transmission system or distribution system, in the event of an interruption of the main power supply to an island; or

(b)produce heat in cases of exceptionally cold weather events,

provided that the operator has signed a declaration in accordance with paragraph 7 of Annex I.

(3) Subject to sub-paragraph (4), where an existing medium combustion plant firing solid fuels falls within sub-paragraph (1) or sub-paragraph (2), an emission limit value for dust of 200mg/Nm3 applies.

(4) In the case of an existing medium combustion plant falling within sub-paragraph (2)(b), the emission limit value for dust in sub-paragraph (3) only applies during any period which has been notified by the appropriate authority to the regulator as an exceptionally cold weather event.

(5) For the purposes of sub-paragraph (2)(a), “transmission system” and “distribution system” have the meanings given in section 4(4) of the Electricity Act 1989.

Limited operating hours - new medium combustion plantsE+W

8.(1) A new medium combustion plant which operates for no more than 500 operating hours per year, as a rolling average over a period of three years, is not required to comply with the emission limit values set out in Part 2 of Annex II, provided that the operator has signed a declaration in accordance with paragraph 7 of Annex I.

(2) Where a new medium combustion plant firing solid fuels falls within sub-paragraph (1), an emission limit value for dust of 100mg/Nm3 applies.

Small and micro isolated systems – existing medium combustion plantsE+W

9.  Existing medium combustion plants which are part of a small isolated system or a micro isolated system are only required to comply with the emission limit values set out in Tables 1, 2 and 3 of Part 1 of Annex II from 1st January 2030.

Plant at gas compressor stations – existing medium combustion plantsE+W

10.  An existing medium combustion plant—

(a)with a rated thermal input greater than 5 megawatts; and

(b)which is used to drive gas compressor stations required to ensure the safety and security of a national gas transmission system,

is only required to comply with the emission limit values for nitrogen oxides set out in Table 3 of Part 1 of Annex II from 1st January 2030.

Temporary derogations – existing and new medium combustion plantsE+W

11.(1) This sub-paragraph applies in relation to a medium combustion plant which normally uses low sulphur fuel, where the operator is unable to comply with the relevant emission limit values for sulphur dioxide in paragraph 6 because of an interruption in the supply of low-sulphur fuel resulting from a serious shortage.

(2) Where sub-paragraph (1) applies, the regulator may grant a derogation from the obligation to comply with those emission limit values for such period, up to a maximum of six months, as the operator satisfies the regulator is justified under the circumstances.

(3) This sub-paragraph applies in relation to a medium combustion plant using only gaseous fuel where—

(a)the plant has to resort exceptionally to the use of other fuels because of an interruption in the supply of gas; and

(b)as a result of using those other fuels, the plant would need to be equipped with secondary abatement equipment in order to comply with the relevant emission limit values for sulphur dioxide, nitrogen oxides and dust in paragraph 6.

(4) Where sub-paragraph (3) applies, the regulator may grant a derogation from the obligation to comply with the relevant emission limit values in paragraph 6—

(a)for a maximum of 10 days; or

(b)for such longer period as the operator satisfies the regulator is justified under the circumstances.

(5) Where the regulator grants a derogation under sub-paragraph (2) or (4), the regulator must inform the appropriate authority immediately.]

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources