- Latest available (Revised)
- Point in Time (04/03/2020)
- Original (As made)
Version Superseded: 31/12/2020
Point in time view as at 04/03/2020.
There are currently no known outstanding effects for the The Environmental Permitting (England and Wales) Regulations 2016, PART 1.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Textual Amendments
F1Schs. 25A, 25B inserted (30.1.2018) by The Environmental Permitting (England and Wales) (Amendment) Regulations 2018 (S.I. 2018/110), regs. 1, 16
1. This Schedule applies—
(a)in relation to every new medium combustion plant from 20th December 2018,
(b)in relation to every existing medium combustion plant from the date specified in regulation 12(1A)(b) or (c), as appropriate.
2.—(1) In this Schedule—
“existing medium combustion plant” means a medium combustion plant—
put into operation before 20th December 2018, or
for which an environmental permit was granted before 19th December 2017, provided that the plant is put into operation no later than 20th December 2018;
“the MCPD” means the Medium Combustion Plant Directive;
“medium combustion plant” means a combustion plant with a rated thermal input equal to or greater than 1 megawatt but less than 50 megawatts, and any combination of combustion plants referred to in article 2(2) or article 4 of the MCPD, provided that—
it does not fall within Article 2(3) or (4) of the MCPD,
it is not installed on an offshore platform situated on, above or below those parts of the sea adjacent to England and Wales from the low water mark to the seaward baseline of the United Kingdom territorial sea,
it is not installed on a gas storage or unloading platform as defined in regulation 2 of the Offshore Combustion Installations (Pollution Prevention and Control) Regulations 2013;
“new medium combustion plant” means a medium combustion plant which is not an existing medium combustion plant.
(2) In sub-paragraph (1), “offshore platform” means any fixed or floating structure which—
(a)is used for the purposes of or in connection with the production of petroleum, and
(b)in the case of a floating structure, is maintained on a station during the course of production,
but does not include any structure where the principal purpose of the use of the structure is the establishment of the existence of petroleum or the appraisal of its characteristics, quality or quantity or the extent of any reservoir in which it occurs.
(3) In sub-paragraph (2), “petroleum” includes any mineral oil or relative hydrocarbon and natural gas existing in its natural condition in strata but does not include coal or bituminous shales or other stratified deposits from which oil can be extracted by destructive distillation.
(4) When interpreting the MCPD for the purposes of this Schedule—
(a)an expression that is defined in Part 1 of these Regulations has the meaning given in that Part;
(b)“permit” means environmental permit;
(c)the competent authority is the regulator;
(d)“general binding rule” means a standard rule published under regulation 26.
3.—(1) The regulator must ensure that every application for the grant of an environmental permit—
(a)includes the information specified in Annex I to the MCPD;
(b)specifies which (if any) of paragraphs 7 to 11 of this Schedule is considered relevant to the application.
(2) Subject to sub-paragraph (3), the regulator must start the procedure for determining an application for the grant of an environmental permit within one month of the operator providing the information referred to in paragraph (1) and must inform the operator of the start of the procedure.
(3) Sub-paragraph (2) applies only when the operator has submitted a duly made application.
4.—(1) The regulator must exercise its relevant functions so as to ensure compliance with the following provisions of the MCPD—
(a)Article 4;
(b)Article 5(1) and (2);
(c)Article 5(6);
(d)Article 6(1);
(e)Article 6(2);
(f)Article 6(7);
(g)Article 6(13);
(h)Article 7 (except Article 7(8));
(i)Article 8(2) and (3);
(j)Article 9.
(2) In exercising its relevant functions, the regulator must ensure that there is no persistent emission of dark smoke, where “dark smoke” has the meaning given in section 3(1) of the Clean Air Act 1993.
(3) In exercising its relevant functions so as to ensure compliance with Article 6(1), (2), (7) or (13) of the MCPD, the regulator must ensure that environmental permits include emission limit values set in accordance with the provisions of Part 2 of this Schedule.]
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: