17.—(1) No part of the authorised development may be commenced until the undertaker has notified the Defence Geographic Centre of the Ministry of Defence of—
(a)the precise location of the authorised development with grid co-ordinates;
(b)the proposed date of commencement of construction;
(c)the height above ground level (in metres) of the tallest structure; and
(d)the maximum extension height (in metres) of any construction equipment.
(2) The undertaker must ensure that the main stack is fitted at the highest practicable point of the structure with an aviation warning omni-directional red light or equivalent infra-red light with a minimum intensity of 25 candela.
(3) The undertaker must notify the Defence Geographic Centre of the Ministry of Defence of the date of completion of the construction of the authorised development within 28 days of completion.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: