Noise during the operational phase

22.—(1) No part of the authorised development may be brought into use until a written scheme has been submitted to and approved in writing by the local planning authority, for the monitoring of noise generated during the operational phases of the development to establish baseline noise conditions and maximum noise levels to be observed. The scheme must specify the locations from where noise must be monitored, the method of noise measurement (which must be in accordance with British Standard 4142:2014 “Methods for rating and assessing industrial and commercial sound” for fixed plant noise and Calculation of Railway Noise 1995, equivalent successor standards or other agreed measurement methodologies appropriate to the circumstances). The written scheme must also specify the periods within which monitoring of operational noise must take place. The written scheme must be implemented and the maximum noise levels identified afterwards be complied with. This monitoring must be subject to annual reviews to establish the frequency of noise monitoring and the need for continued monitoring.

(2) Prior to installation, details of all mechanical and ventilation plant must be submitted to and approved by the local planning authority. Any fixed plant or ventilation equipment must be installed and operated in accordance with manufacturers’ instructions at all times.

(3) Subject to health and safety requirements, broadband reversing alarms must be employed on mobile plant.

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources