Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
24.—(1) No phase of the authorised development is to commence until a localised contamination report for that phase has been submitted to and approved in writing by the local planning authority.
(2) No development is to commence on any specifically identified localised areas of the site potentially affected by contamination (as detailed in the Preliminary Sources Study Reports (“PSSR”) documents contained within the environmental statement (Document 5.2)) until further investigations and a Risk Based Land Contamination Assessment has been undertaken in line with the recommendations made within the PSSR for that localised area of the site and this has been submitted to and approved in writing by the local planning authority. The Risk Based Land Contamination Assessment must be carried out in accordance with—
(a)British Standard 10175:2011+A1:2013 “Investigation Of Potentially Contaminated Sites Code of Practice”;
(b)British Standard 8576:2013 “Guidance on Investigations for Ground Gas – Permanent Gases and Volatile Organic Compounds (VOCs)”;
(c)British Standard 8485:2007 “Code of Practice for the Characterisation and Remediation from Ground Gas in Affected Developments”; and
(d)CLR 11 “Model Procedures for the Management of Land Contamination”, published by The Environment Agency 2004 (“CLR 11”).
(3) Should any unacceptable risks be identified in the Risk Based Land Contamination Assessment, a Remedial Scheme and a Verification Plan must be prepared and submitted to and agreed in writing by the local planning authority. The Remedial Scheme must be prepared in accordance with the requirements of CLR 11. The Verification Plan must be prepared in accordance with the requirements of—
(a)Evidence Report on the Verification of Remediation of Land Contamination Report SC030114/R1, published by the Environment Agency 2010; and
(b)CLR 11.
(4) If, during the course of development, previously unidentified contamination is discovered, development must cease on that localised area of the site and the contamination must be reported in writing to the local planning authority within 10 working days. Prior to the recommencement of development on that localised area of the site, suitable investigation and Risk Based Land Contamination Assessment for the discovered contamination (to include any required amendments to the Remedial Scheme and Verification Plan) must be submitted to and approved in writing by the local planning authority. The development must then be implemented in accordance with the details approved by the local planning authority and, unless otherwise agreed in writing by the local planning authority, retained as such in perpetuity.
Commencement Information
I1Sch. 2 para. 24 in force at 2.2.2016, see art. 1
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: