5. The undertaker must use reasonable endeavours to complete the highway works identified in column (1) of the table below by no later than the stage of development set out in column (3) of the table below or such alternative later triggers as are agreed by the relevant body identified in column (4) and the local planning authority.
Highway Works
(1) Item as identified on the highway works components plans (Document 2.13) | (2) Description | (3) Stage of Development | (4) Relevant Body |
---|---|---|---|
(i) | A453 site access and Kegworth Bypass Junction (not including the bypass itself). | To be completed prior to the occupation of first warehouse to be occupied. | Highways England |
(ii) | A50 eastbound to M1 southbound and Junction 24 interchange links; M1 southbound to A50 interchange link; improvements to M1 southbound from Junction 24A to Junction 24; and alterations to Junction 24 roundabout east of M1. | To be completed prior to the occupation of first warehouse to be occupied. | Highways England |
(iii) | Construction of local access road to Lockington. | To be completed prior to the occupation of first warehouse to be occupied. | Leicestershire County Council |
(iv) | Diseworth Lane alterations. | To be completed prior to the occupation of the first warehouse to be occupied. | Leicestershire County Council |
(v) | Church Street works. | To be completed prior to the occupation of the first warehouse to be occupied. | Leicestershire County Council |
(vi) | Alterations to Junction 24 roundabout west of M1; improvements to A50 and A453 west of M1; and alterations to M1 northbound exit slip road. | To be completed prior to the occupation of the first warehouse to be occupied. | Highways England |
(vii) | Kegworth Bypass including alterations to Ashby Road and Whatton Road. | To be completed prior to the occupation of more than 185,800 square metres (gross internal area) of warehouse floorspace. | Leicestershire County Council |
(viii) | M1 overbridges from Ashby Road to A453 and from Kegworth Bypass to A453. | To be completed prior to the occupation of more than 185,800 square metres (gross internal area) of warehouse floorspace. | (1) Highways England (bridge structures) (2) Leicestershire County Council (highway) |
(ix) | Warren Lane access and public footpath and cycle track adjacent to A50 interchange links connecting Warren Lane and A453 eastbound. | To be completed prior to the occupation of the first warehouse to be occupied. | Leicestershire County Council |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: