Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
26.—(1) Economic operators that, under the law of the member State in which they are established, are entitled to provide the relevant service, shall not be rejected solely on the ground that under the law of England and Wales or, as the case may be, Northern Ireland, they would be required to be either natural or legal persons.
(2) Legal persons may be required to indicate, in the tender or in the application, the names and relevant professional qualifications of the staff to be responsible for the performance of the contract in question.
(3) Groups of economic operators, including temporary associations, may participate in concession contract award procedures and shall not be required by contracting authorities or utilities to have a specific legal form in order to submit a tender or an application.
(4) Where necessary, contracting authorities or utilities may clarify in the concession documents how groups of economic operators are to meet the requirements as to economic and financial standing or technical and professional ability referred to in regulation 38 provided that this is justified by objective reasons and is proportionate.
(5) Any conditions for the performance of a concession contract by such groups of economic operators which are different from those imposed on individual participants shall also be justified by objective reasons and shall be proportionate.
(6) Contracting authorities or utilities may require groups of economic operators to assume a specific legal form once they have been awarded the contract, to the extent that such a change is necessary for the satisfactory performance of the contract.
27. Any references to nomenclatures in the context of the award of concession contracts shall be made using the CPV.
28.—(1) A contracting authority or utility shall not disclose information which has been forwarded to it by an economic operator and designated by that economic operator as confidential, including, but not limited to, technical or trade secrets and the confidential aspects of tenders.
(2) Paragraph (1) is without prejudice to—
(a)any other provisions of these Regulations, including the obligations relating to the advertising of awarded concession contracts and the provision of information to candidates and tenderers set out in regulations 32 and 40 respectively;
(b)the Freedom of Information Act 2000 M1;
(c)any other requirement, or permission, for the disclosure of information that is applicable under the law of England and Wales or, as the case may be, Northern Ireland.
(3) Contracting authorities and utilities may impose on economic operators requirements aimed at protecting the confidential nature of information which they make available throughout the concession contract award procedure.
29.—(1) Except where the use of electronic means is mandatory in accordance with regulations 33(1) and 34, contracting authorities and utilities may choose one or more of the following means of communication for all communication and information exchange—
(a)electronic means;
(b)post or facsimile;
(c)oral communication, including telephone, in respect of communications other than the essential elements of a concession contract award procedure, and provided that the content of the oral communication is documented to a sufficient degree on a durable medium;
(d)hand delivery certified by an acknowledgement of receipt.
(2) The means of communication chosen shall be generally available and non-discriminatory, and shall not restrict economic operators' access to the concession contract award procedure.
(3) The tools and devices to be used for communicating by electronic means, and their technical characteristics, shall be interoperable with information and communication technology products in general use.
(4) In all communication, exchange and storage of information, contracting authorities and utilities shall ensure that the integrity of data and the confidentiality of applications and tenders are preserved.
(5) Contracting authorities and utilities shall examine the content of applications and tenders only after the time limit set for submitting them has expired.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: