You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
The Concession Contracts Regulations 2016, Section 17 is up to date with all changes known to be in force on or before 31 October 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
17.—(1) A concession contract awarded by a contracting authority or a utility referred to in regulation 5(1)(a) to a legal person falls outside the scope of these Regulations where all of the following conditions are fulfilled—
(a)the contracting authority or utility exercises over the legal person concerned a control which is similar to that which it exercises over its own departments;
(b)more than 80% of the activities of the controlled legal person are carried out in the performance of tasks entrusted to it by the controlling contracting authority or utility or by other legal persons controlled by that contracting authority or utility; and
(c)there is no direct private capital participation in the controlled legal person with the exception of non-controlling and non-blocking forms of private capital participation required by national legislative provisions, in conformity with the Treaties, which do not exert a decisive influence on the controlled legal person.
(2) A concession contract also falls outside the scope of these Regulations where a controlled legal person which is a contracting authority or utility referred to in regulation 5(1)(a) awards a concession contract to—
(a)its controlling contracting authority or utility, or
(b)another legal person controlled by the same contracting authority or utility,
provided that there is no direct private capital participation in the legal person being awarded the concession contract with the exception of non-controlling and non-blocking forms of private capital participation required by national legislative provisions, in conformity with the Treaties, which do not exert a decisive influence on the legal person being awarded the contract.
(3) A contracting authority or utility shall be deemed to exercise over a legal person a control similar to that which it exercises over its own departments within the meaning of paragraph (1)(a) where—
(a)it exercises a decisive influence over both strategic objectives and significant decisions of the controlled legal person, or
(b)that control is exercised by another legal person which is itself controlled in the same way by the contracting authority or utility,
and references to “control”, “controlled” and “controlling” in paragraphs (1) to (3) shall be interpreted accordingly.
(4) A contracting authority or utility referred to in regulation 5(1)(a) which does not exercise over a legal person control within the meaning of paragraph (3) may nevertheless award a concession contract to that legal person without applying these Regulations where all of the following conditions are fulfilled—
(a)the contracting authority or utility exercises jointly with other contracting authorities or utilities a control over that legal person which is similar to that which they exercise over their own departments;
(b)more than 80% of the activities of that legal person are carried out in the performance of tasks entrusted to it by the controlling contracting authorities or utilities or by other legal persons controlled by the same contracting authorities or utilities; and
(c)there is no direct private capital participation in the controlled legal person with the exception of non-controlling and non-blocking forms of private capital participation required by national legislative provisions, in conformity with the Treaties, which do not exert a decisive influence on the controlled legal person.
(5) For the purposes of paragraph (4)(a), contracting authorities or utilities exercise joint control over a legal person where all of the following conditions are fulfilled—
(a)the decision-making bodies of the controlled legal person are composed of representatives of all participating contracting authorities or utilities;
(b)those contracting authorities or utilities are able to jointly exert decisive influence over the strategic objectives and significant decisions of the controlled legal person; and
(c)the controlled legal person does not pursue any interests which are contrary to those of the controlling contracting authorities or utilities.
(6) For the purposes of paragraph (5)(a), individual representatives may represent several or all of the participating contracting authorities or utilities.
(7) A concession contract concluded exclusively between two or more contracting authorities or utilities referred to in regulation 5(1)(a) falls outside the scope of these Regulations where all of the following conditions are fulfilled—
(a)the contract establishes or implements a co-operation between the participating contracting authorities or utilities with the aim of ensuring that public services they have to perform are provided with a view to achieving objectives they have in common;
(b)the implementation of that co-operation is governed solely by considerations relating to the public interest; and
(c)the participating contracting authorities or utilities perform on the open market less than 20% of the activities concerned by the co-operation.
(8) For the determination of the percentage of activities referred to in paragraphs (1)(b), (4)(b) and (7)(c), the average total turnover, or an appropriate alternative activity-based measure such as costs incurred by the relevant legal person, contracting authority or utility referred to regulation 5(1)(a) with respect to services, supplies and works for the 3 years preceding the concession contract award shall be taken into consideration.
(9) Where, because of—
(a)the date on which the relevant legal person, contracting authority or utility was created or commenced activities, or
(b)a reorganisation of its activities,
the turnover, or alternative activity-based measure such as costs, are either not available for the preceding 3 years or no longer relevant, it shall be sufficient to show that the measurement of activity is credible, particularly by means of business projections.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: