42.—(1) In the concession documents, the contracting authority or utility may ask the tenderer to indicate in its tender any share of the concession contract that it may intend to subcontract to third parties and any proposed subcontractors.
(2) Paragraph (1) is without prejudice to the question of the concessionaire’s liability.
(3) In the case of a works concession contract and in respect of services to be provided at a facility under the oversight of the contracting authority or utility, after the award of the concession contract and at the latest when the performance of the concession contract commences, the contracting authority or utility shall require the concessionaire to notify to the contracting authority or utility the name, contact details and legal representatives of its subcontractors involved in such works or services, in so far as known at the time.
(4) The contracting authority or utility shall require the concessionaire to notify it of—
(a)any changes to the information notified under paragraph (3) during the course of the concession contract; and
(b)the name, contact details and legal representatives of any new subcontractors which it subsequently involves in such works or services.
(5) Paragraphs (3) and (4) do not apply to suppliers.
(6) Contracting authorities and utilities may extend the obligations provided for in paragraphs (3) and (4) to, for example—
(a)services concession contracts (other than those concerning services to be provided at the facilities under the oversight of the contracting authority or utility) or suppliers involved in works concession contracts or services concession contracts;
(b)subcontractors of the concessionaire’s subcontractors or subcontractors further down the subcontracting chain.
(7) Contracting authorities and utilities may verify whether there are grounds for exclusion of subcontractors under regulation 38(8) to (25).
(8) In such cases, the contracting authority or utility—
(a)shall require that the economic operator replaces a subcontractor in respect of which the verification has shown that there are compulsory grounds for exclusion; and
(b)may require that the economic operator replaces a subcontractor in respect of which the verification has shown that there are non-compulsory grounds for exclusion.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: