The Concession Contracts Regulations 2016, Section 9 is up to date with all changes known to be in force on or before 31 October 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
9.—(1) These Regulations apply to concession contracts the value of which are equal to or greater than [F1£4,733,252].
F2(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(3) For the purposes of paragraph (1), the value of a concession contract shall be the total turnover of the concessionaire generated over the duration of the contract, net of value added tax, as estimated by the contracting authority or utility, in consideration for the works and services which are the object of the concession contract and for the supplies incidental to such works and services.
(4) That estimate shall be calculated as at the moment at which the concession notice is [F3submitted] for publication in accordance with regulation 33 or, in cases where such notice is not provided for, at the moment at which the contracting authority or utility commences the concession contract award procedure, for example by contacting economic operators in relation to the concession contract.
(5) But if the value as estimated at the time of the award is more than 20% higher than the estimate calculated in accordance with paragraph (4), the former shall be used for the purposes of this regulation.
(6) The estimated value of the concession contract shall be calculated using an objective method specified in the concession documents.
(7) When calculating the estimated value of the concession contract, contracting authorities and utilities shall, where applicable, take into account in particular—
(a)the value of any form of option and any extension of the duration of the concession contract;
(b)revenue from the payment of fees and fines by the users of the works or services other than those collected on behalf of the contracting authority or utility;
(c)payments or any other financial advantages, in any form, from the contracting authority or utility or any other public authority to the concessionaire, including compensation for compliance with a public service obligation and public investment subsidies;
(d)the value of grants or any other financial advantages, in any form, from third parties for the performance of the concession contract;
(e)revenue from sales of any assets which are part of the concession contract;
(f)the value of all the supplies and services that are made available to the concessionaire by the contracting authorities or utilities, provided that they are necessary for executing the works or providing the services;
(g)any prizes or payments to candidates or tenderers.
(8) The choice of the method used to calculate the estimated value of a concession contract shall not be made with the intention of excluding it from the scope of these Regulations.
(9) A concession contract shall not be subdivided with the effect of preventing it from falling within the scope of these Regulations, unless justified by objective reasons.
(10) Where a proposed work or proposed provision of services may result in concession contracts being awarded in the form of separate lots, account shall be taken of the total estimated value of all such lots.
(11) Where the aggregate value of the lots is equal to or greater than the threshold mentioned in paragraph (1), these Regulations shall apply to the awarding of each lot.
Textual Amendments
F1Sum in reg. 9(1) substituted (31.12.2020) by The Public Procurement (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1319), regs. 1(2), 8(5)(a) (with Sch. paras. 3-5)
F2Reg. 9(2) omitted (31.12.2020) by virtue of The Public Procurement (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1319), regs. 1(2), 8(5)(b) (with Sch. paras. 3-5)
F3Word in reg. 9(4) substituted (31.12.2020) by The Public Procurement (Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1319), regs. 1(2), 8(5)(c) (with Sch. paras. 3-5)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: