The Thorpe Marsh Gas Pipeline Order 2016

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Development consent etc. granted by Order

3.  Subject to the provisions of this Order and to the Requirements in Part 2 of Schedule 1, the undertaker is granted development consent for the authorised development in Part 1 of Schedule 1 to be carried out within the Order limits, and Schedule 1 has effect for that purpose.