The National Grid (Hinkley Point C Connection Project) Order 2016

 Help about what version

What Version

 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made).

England Coast path

45.—(1) No works to—

(a)dismantle the existing overhead lines—

(i)between pylon VQ1 and VQ2, and

(ii)between pylon ZZ4 and ZZ5, and

(b)string the proposed new overhead lines—

(i)between pylon VQ3A and VQ3B, and

(ii)between pylon ZZ4 and ZZ5,

may commence until consent given by the Joint Councils in respect of the diversion of footpaths WL23/71 and WL23/61.

(2) The consent of the Joint Councils referred to in paragraph (1) must not be unreasonably withheld.