Search Legislation

The A19/A1058 Coast Road (Junction Improvement) Development Consent Order 2016

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Landscaping

4.—(1) No part of the authorised development is to commence until a written landscaping scheme for that part has been submitted to and approved in writing by the relevant planning authority.

(2) No part of the authorised development including vegetation clearance is to commence until an arboricultural walkover survey and tree survey for that part taking due regard to the guidance in British Standard 5837:2012 have been undertaken to identify any significant constraints posed by trees.

(3) The landscaping scheme prepared under sub-paragraph (1) must be based on the preliminary landscape design contained in Appendix 6.3 to the environmental report and the results of the surveys undertaken under sub-paragraph (2).

(4) The landscaping scheme prepared under sub-paragraph (1) must include details of hard and soft landscaping works, including—

(a)location, number, species, size and planting density of any proposed planting;

(b)cultivation, importing of materials and other operations to ensure plant establishment;

(c)proposed finished ground levels;

(d)hard surfacing materials;

(e)details of existing trees to be retained, with measures for their protection during the construction period; and

(f)implementation timetables for all landscaping works.

Back to top