Capital dredging, disposal conditions and debris
34.—(1) The undertaker must agree a capital dredge and disposal strategy with the MMO at least 4 weeks before the commencement of any licensed activities.
(2) If any disposal or dredging activities are to take place after 1st October 2017—
(a)the undertaker must submit a sediment sampling plan to the MMO for approval at least 6 months prior to that dredging or disposal activity being carried out;
(b)the sediment sampling and analysis of the sediment must be completed by a laboratory validated by the MMO at least 6 weeks prior to the dredging or disposal activity being carried out; and
(c)the dredging and disposal activity must not be carried out without the consent of the MMO.