SCHEDULES

SCHEDULE 9FOR THE PROTECTION OF THE PIPELINE CORRIDOR AND PROTECTED CROSSINGS

Further provisions about works

10.—(1) Where temporary crossings for construction traffic are to be used, other than where the pipelines are under a carriageway of adequate standard of construction, then the crossing points must be suitably reinforced with sleepers or road plates or a specially constructed reinforced concrete raft or by installing a temporary bridge over the pipeline as necessary.

(2) Details of proposed temporary crossing points referred to in sub-paragraph (1) must be notified to the owner and operator of the pipeline in accordance with paragraph 4.