The Meaford Gas Fired Generating Station Order 2016

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Benefit of Order

6.—(1) Subject to paragraph (2) and article 7 (consent to transfer benefit of Order), the provisions of this Order have effect solely for the benefit of the undertaker.

(2) Paragraph (1) does not apply to—

(a)numbered work 2A(i) and numbered work 2A(ii) for which consent is granted by this Order for the benefit of the undertaker and National Grid; and

(b)numbered work 3 for which consent is granted by this Order for the benefit of the undertaker and WPD.