Interpretation

1.  In this Schedule—

“commence” means beginning to carry out any material operation (as defined in section 56(4) of the 1990 Act) forming part of the authorised development excluding permitted preliminary works and the words “commencement” and “commenced” and cognate expressions shall be construed accordingly;

“the design objectives statement” means the design objectives contained within the summary of design objectives at chapter 2 of the design and access statement;

“illustrative cross sections drawing” means the illustrative cross sections through planting strip adjacent to canal drawing with drawing number 5105324-MEA-DRG-086 Rev 0 dated 24 September 2015 that was submitted as an appendix to Document 10.7 (Applicant’s comments on the Local Impact Report) dated 22 October 2015;

“illustrative foul and surface water drainage plan” means the illustrative foul and surface water drainage strategy plan with reference number 2.5.5 and submitted with the application and regulation 5(2)(o) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009(1);

“illustrative landscaping plan” means the illustrative landscaping plan with reference number 2.7.2 and submitted with the application under regulation 5(2)(o) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009;

“permitted preliminary works” means the intrusive ground investigation works carried out pursuant to requirement 6 (ground investigation); and

“start-up and shut-down” means the periods of 30 minutes before the opening up of construction sites (start-up) and 30 minutes following the end of the working day (shut-down), during which the arrival of workers, changing into and out of work wear, pre-job briefing and leaving the site prior to closing and securing the site take place.

(1)

S.I. 2009/2264, as amended by S.I. 2014/2381.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources