Time limit for exercise of authority to acquire land compulsorilyE+W+S

20.—(1) After 15th August 2021—

(a)no notice to treat may be served under Part 1 of the 1965 Act; and

(b)no declaration may be executed under section 4 of the 1981 Act(1), as applied by article 22 (application of Compulsory Purchase (Vesting Declarations) Act 1981).

(2) The authority conferred by article 26 ceases at the end of 15th August 2021, but nothing in this paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land was entered, and possession taken, on or before that date.

Commencement Information

I1Art. 20 in force at 7.9.2016, see art. 1(2)

(1)

Section 4 is amended, from a date to be appointed, by sections 184 and 185 of, and paragraph 2 of Schedule 18 to, the Housing and Planning Act 2016 (c.22).