SCHEDULE 12Protective provisions

PART 10Protection for ConocoPhillips (U.K.) Limited

I13

Not less than 28 days before commencing any part of the authorised development or the operation of the authorised development that is near to and would or may have an effect on the operation and maintenance of the pipeline and access to it, the relevant undertaker must submit to ConocoPhillips plans and sections of the proposed works and such further particulars as ConocoPhillips may, within 28 days from the day on which plans and sections are submitted under this paragraph, reasonably require.