Search Legislation

The Hornsea Two Offshore Wind Farm Order 2016

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Paragraph 14

 Help about opening options

Alternative versions:

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Hornsea Two Offshore Wind Farm Order 2016. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

14.  Without limiting paragraph 12, it is not be reasonable for an approving party to withhold or delay any consent or approval under this Part in relation to specified works in, on, under, or over the grid connection land solely on the basis of thermal interaction between the circuit and any adjacent circuit, whether existing or proposed, where it has been demonstrated that there will be no material thermal interaction, which is deemed to have been demonstrated where the separation between the circuits is 6 metres or more (from the centre line of each circuit).E+W+S

Commencement Information

I1Sch. 12 Pt. 11 para. 14 in force at 7.9.2016, see art. 1(2)

Back to top