Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Article 4
Commencement Information
I1Sch. 2 Pt. 1 in force at 15.9.2016, see art. 1
Drawing Title | Sheet Number | Drawing Number |
---|---|---|
Works plans – Key plan | Key Plan | W001 |
Works plan | Sheet 1 of 8 | W002 |
Sheet 2 of 8 | W003 | |
Sheet 3 of 8 | W004 | |
Sheet 4 of 8 | W005 | |
Sheet 5 of 8 | W006 | |
Sheet 6 of 8 | W007 | |
Sheet 7 of 8 | W008 | |
Sheet 8 of 8 | W009 |
Commencement Information
I2Sch. 2 Pt. 2 in force at 15.9.2016, see art. 1
Drawing title | Sheet number | Drawing number |
---|---|---|
Land Plans – Key plan | Key Plan | L001 |
Land plan | Sheet 1 of 17 | L002 |
Sheet 2 of 17 | L003 | |
Sheet 3 of 17 | L004 | |
Sheet 4 of 17 | L005 | |
Sheet 5 of 17 | L006 | |
Sheet 6 of 17 | L007 | |
Sheet 7 of 17 | L008 | |
Sheet 8 of 17 | L009 | |
Sheet 9 of 17 | L0010 | |
Sheet 10 of 17 | L0011 | |
Sheet 11 of 17 | L0012 | |
Sheet 12 of 17 | L0013 | |
Sheet 13 of 17 | L0014 | |
Sheet 14 of 17 | L0015 | |
Sheet 15 of 17 | L0016 | |
Sheet 16 of 17 | L0017 | |
Sheet 17 of 17 | L0018 |
Commencement Information
I3Sch. 2 Pt. 3 in force at 15.9.2016, see art. 1
Drawing Title | Sheet Number | Drawing Number |
---|---|---|
Access and rights of way plans – Key plan | Key Plan | A001 |
Access and rights of way plan | Sheet 1 of 8 | A002 |
Sheet 2 of 8 | A003 | |
Sheet 3 of 8 | A004 | |
Sheet 4 of 8 | A005 | |
Sheet 5 of 8 | A006 | |
Sheet 6 of 8 | A007 | |
Sheet 7 of 8 | A008 | |
Sheet 8 of 8 | A009 |
Commencement Information
I4Sch. 2 Pt. 4 in force at 15.9.2016, see art. 1
Document | Date | Document Title |
---|---|---|
6.1 | 15 April 2015 | Introduction |
6.2 | 15 April 2015 | Scheme Description |
6.3 | 15 April 2015 | Design Iterations and Alternatives Considered |
6.3.1 | 15 April 2015 | Appendix 3.1 Strategic Options Report |
6.3.2 | 15 April 2015 | Appendix 3.2 Alternatives - Route Corridor Investigation Study |
6.4 | 15 April 2015 | Appendix 3.3 Alternatives - Crossing Options Report A |
6.4.1 | 15 April 2015 | EIA Methodology and Construction Environmental Management |
6.4.2 | 15 April 2015 | Appendix 4.1 PINS Scoping Opinion Comments |
6.5 | 15 April 2015 | Air Quality |
6.5.1 | 15 April 2015 | Appendix 5.1 Dust risk Assessment |
6.6 | 15 April 2015 | Cultural Heritage |
6.6.1 | 15 April 2015 | Appendix 6.1 Desk-Based Assessment |
6.6.2 | 15 April 2015 | Appendix 6.2 Aerial Photograph Analysis at Paull |
6.6.3 | 15 April 2015 | Appendix 6.3 Geophysical Surveys Undertaken at Paull |
6.6.4 | 15 April 2015 | Appendix 6.4 Geophysical surveys Undertaken at Goxhill |
6.6.5 | 15 April 2015 | Appendix 6.5 Southend Bypass Geophysical Survey |
6.7 | 15 April 2015 | Ecology and Nature Conservation |
6.7.1 | 15 April 2015 | Appendix 7.1 Technical Appendix |
6.7.2 | 15 April 2015 | Appendix 7.2 Potentially Excepted Information |
6.8 | 15 April 2015 | Update Deadline 8? |
6.8.1 | 15 April 2015 | Geology and Soils |
6.8.2 | 15 April 2015 | Appendix 8.1 Environmental Agency and Local Authority Responses |
6.8.2 | 15 April 2015 | Appendix 8.2 Desk Study Report Plan 1 |
6.8.2 | 15 April 2015 | Appendix 8.2 Desk Study Report Plan 2 |
6.8.3.2 | 15 April 2015 | Appendix 8.2 Desk Study Report Plan 3 |
6.8.3 | 15 April 2015 | Appendix 8.3 Ground Investigation Report |
6.8.3.1 | 12 October 2015 | Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 1 |
6.8.3.2 | 12 October 2015 | Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 2 |
6.8.3.3 | 12 October 2015 | Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 3 |
6.8.3.4 | 12 October 2015 | Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 4 |
6.8.3.5 | 12 October 2015 | Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 5 |
6.8.3.6 | 12 October 2015 | Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 6 |
6.8.3.7 | 12 October 2015 | Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 7 |
6.8.3.8 | 12 October 2015 | Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 8 |
6.8.3.9 | 12 October 2015 | Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 9 |
6.8.3.10 | 12 October 2015 | Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 10 |
6.8.3.11 | 02 November 2015 | Appendix 8.3 Addendum - Phase II Test Results and Factual Report |
6.8.4 | 15 April 2015 | Appendix 8.4 Paull Holme Strays Investigation Report |
6.8.5 | 15 April 2015 | Appendix 8.5 Chalk Report |
6.8.6 | 15 April 2015 | Appendix 8.6 Geophysical Survey Report 1 |
6.8.6 | 15 April 2015 | Appendix 8.6 Geophysical Survey Report 2 |
6.8.6 | 15 April 2015 | Appendix 8.6 Geophysical Survey Report 3 |
6.8.7 | 15 April 2015 | Appendix 8.7 Information Relating to Stoneledge Field Investigation |
6.8.8 | 15 April 2015 | Appendix 8.8 Responses from Lincolnshire Environmental Records Centre East Yorkshire RIGS Group |
6.8.9 | 15 April 2015 | Appendix 8.9 Unexploded Ordnance Report |
6.9 | 15 April 2015 | Landscape and Visual Amenity |
6.10 | 15 April 2015 | Noise and Vibration |
6.10.1 | 15 April 2015 | Appendix 10.1 Noise Monitoring Installation Sheets and Time History |
6.10.2 | 15 April 2015 | Appendix 10.2 Noise Model Inputs |
6.10.3 | 15 April 2015 | Appendix 10.3 Noise Model Outputs |
6.11 | 15 April 2015 | Socio-Economics and Land Use |
6.11.1 | 15 April 2015 | Appendix 11.1 Agricultural Land Survey |
6.12 | 15 April 2015 | Traffic and Transport |
6.13 | 15 April 2015 | Water Resources |
6.13.1 | 15 April 2015 | Appendix 13.1 Water Framework Directive Assessment |
6.13.2A | 13 January 2016 | Appendix 13.2 Initial Site Water Management Plan |
6.13.2.1 | 13 January 2016 | Comparison between Initial Site Water Management Plan versions 6.13.2 and 6.13.2A |
16.13.3 | 15 April 2015 | Appendix 13.3 Hydrogeological Impact Assessment |
6.13.3.1 | 12 October 2015 | Appendix 13.3 Addendum - Mini-Pumping Test Results and Factual Report |
6.13.3.2 | 12 October 2015 | Appendix 13.3 Addendum Report to Hydrogeological Impact Assessment |
6.14 | 15 April 2015 | Cumulative Effects |
6.15 | 15 April 2015 | Cumulative Effects |
6.16 | 15 April 2015 | Screening Opinions |
6.17 | 15 April 2015 | Scoping Opinion |
6.18 | 15 April 2015 | EIA Regulations Publicity Requirements |
6.19 | 15 April 2015 | Non-Technical Summary |
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: