Article 4

SCHEDULE 2E+W+SPlans

PART 1E+W+SWorks plans

Commencement Information

I1Sch. 2 Pt. 1 in force at 15.9.2016, see art. 1

Table 2

Drawing TitleSheet NumberDrawing Number
Works plans – Key planKey PlanW001
Works planSheet 1 of 8W002
Sheet 2 of 8W003
Sheet 3 of 8W004
Sheet 4 of 8W005
Sheet 5 of 8W006
Sheet 6 of 8W007
Sheet 7 of 8W008
Sheet 8 of 8W009

PART 2E+W+SLand plans

Commencement Information

I2Sch. 2 Pt. 2 in force at 15.9.2016, see art. 1

Table 3

Drawing titleSheet numberDrawing number
Land Plans – Key planKey PlanL001
Land planSheet 1 of 17L002
Sheet 2 of 17L003
Sheet 3 of 17L004
Sheet 4 of 17L005
Sheet 5 of 17L006
Sheet 6 of 17L007
Sheet 7 of 17L008
Sheet 8 of 17L009
Sheet 9 of 17L0010
Sheet 10 of 17L0011
Sheet 11 of 17L0012
Sheet 12 of 17L0013
Sheet 13 of 17L0014
Sheet 14 of 17L0015
Sheet 15 of 17L0016
Sheet 16 of 17L0017
Sheet 17 of 17L0018

PART 3E+W+SAccess and rights of way plans

Commencement Information

I3Sch. 2 Pt. 3 in force at 15.9.2016, see art. 1

Table 4

Drawing TitleSheet NumberDrawing Number
Access and rights of way plans – Key planKey PlanA001
Access and rights of way planSheet 1 of 8A002
Sheet 2 of 8A003
Sheet 3 of 8A004
Sheet 4 of 8A005
Sheet 5 of 8A006
Sheet 6 of 8A007
Sheet 7 of 8A008
Sheet 8 of 8A009

PART 4E+W+SEnvironmental statement

Commencement Information

I4Sch. 2 Pt. 4 in force at 15.9.2016, see art. 1

Table 5

DocumentDateDocument Title
6.115 April 2015Introduction
6.215 April 2015Scheme Description
6.315 April 2015Design Iterations and Alternatives Considered
6.3.115 April 2015Appendix 3.1 Strategic Options Report
6.3.215 April 2015Appendix 3.2 Alternatives - Route Corridor Investigation Study
6.415 April 2015Appendix 3.3 Alternatives - Crossing Options Report A
6.4.115 April 2015EIA Methodology and Construction Environmental Management
6.4.215 April 2015Appendix 4.1 PINS Scoping Opinion Comments
6.515 April 2015Air Quality
6.5.115 April 2015Appendix 5.1 Dust risk Assessment
6.615 April 2015Cultural Heritage
6.6.115 April 2015Appendix 6.1 Desk-Based Assessment
6.6.215 April 2015Appendix 6.2 Aerial Photograph Analysis at Paull
6.6.315 April 2015Appendix 6.3 Geophysical Surveys Undertaken at Paull
6.6.415 April 2015Appendix 6.4 Geophysical surveys Undertaken at Goxhill
6.6.515 April 2015Appendix 6.5 Southend Bypass Geophysical Survey
6.715 April 2015Ecology and Nature Conservation
6.7.115 April 2015Appendix 7.1 Technical Appendix
6.7.215 April 2015Appendix 7.2 Potentially Excepted Information
6.815 April 2015Update Deadline 8?
6.8.115 April 2015Geology and Soils
6.8.215 April 2015Appendix 8.1 Environmental Agency and Local Authority Responses
6.8.215 April 2015Appendix 8.2 Desk Study Report Plan 1
6.8.215 April 2015Appendix 8.2 Desk Study Report Plan 2
6.8.3.215 April 2015Appendix 8.2 Desk Study Report Plan 3
6.8.315 April 2015Appendix 8.3 Ground Investigation Report
6.8.3.112 October 2015Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 1
6.8.3.212 October 2015Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 2
6.8.3.312 October 2015Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 3
6.8.3.412 October 2015Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 4
6.8.3.512 October 2015Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 5
6.8.3.612 October 2015Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 6
6.8.3.712 October 2015Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 7
6.8.3.812 October 2015Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 8
6.8.3.912 October 2015Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 9
6.8.3.1012 October 2015Appendix 8.3 Addendum - Phase I Test Results and Factual Report Volume 10
6.8.3.1102 November 2015Appendix 8.3 Addendum - Phase II Test Results and Factual Report
6.8.415 April 2015Appendix 8.4 Paull Holme Strays Investigation Report
6.8.515 April 2015Appendix 8.5 Chalk Report
6.8.615 April 2015Appendix 8.6 Geophysical Survey Report 1
6.8.615 April 2015Appendix 8.6 Geophysical Survey Report 2
6.8.615 April 2015Appendix 8.6 Geophysical Survey Report 3
6.8.715 April 2015Appendix 8.7 Information Relating to Stoneledge Field Investigation
6.8.815 April 2015Appendix 8.8 Responses from Lincolnshire Environmental Records Centre East Yorkshire RIGS Group
6.8.915 April 2015Appendix 8.9 Unexploded Ordnance Report
6.915 April 2015Landscape and Visual Amenity
6.1015 April 2015Noise and Vibration
6.10.115 April 2015Appendix 10.1 Noise Monitoring Installation Sheets and Time History
6.10.215 April 2015Appendix 10.2 Noise Model Inputs
6.10.315 April 2015Appendix 10.3 Noise Model Outputs
6.1115 April 2015Socio-Economics and Land Use
6.11.115 April 2015Appendix 11.1 Agricultural Land Survey
6.1215 April 2015Traffic and Transport
6.1315 April 2015Water Resources
6.13.115 April 2015Appendix 13.1 Water Framework Directive Assessment
6.13.2A13 January 2016Appendix 13.2 Initial Site Water Management Plan
6.13.2.113 January 2016Comparison between Initial Site Water Management Plan versions 6.13.2 and 6.13.2A
16.13.315 April 2015Appendix 13.3 Hydrogeological Impact Assessment
6.13.3.112 October 2015Appendix 13.3 Addendum - Mini-Pumping Test Results and Factual Report
6.13.3.212 October 2015Appendix 13.3 Addendum Report to Hydrogeological Impact Assessment
6.1415 April 2015Cumulative Effects
6.1515 April 2015Cumulative Effects
6.1615 April 2015Screening Opinions
6.1715 April 2015Scoping Opinion
6.1815 April 2015EIA Regulations Publicity Requirements
6.1915 April 2015Non-Technical Summary