24.—(1) Prior to the commencement of undergrounding works within Work No. 2, a final frac-out contingency plan consistent with the frac-out contingency plan shall be submitted to and approved in writing by the relevant planning authority in consultation with Natural Resources Wales. The final frac-out contingency plan shall include—
(a)the persons responsible for implementing the measures to be set out within the plan:
(b)design protocols and measures to be implemented for the protection of sensitive ecological receptors;
(c)confirmation of the suitability of the formations to be drilled;
(d)measures to monitor the drilling process for frac-out; and
(e)the measures to be initiated to protected sensitive ecological receptors should frac-out occur.
(2) The final frac-out contingency plan must be implemented as approved.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: