63.—(1) A competent authority, before deciding to undertake, or give any consent, permission or other authorisation for, a plan or project which—
(a)is likely to have a significant effect on a European site or a European offshore marine site (either alone or in combination with other plans or projects), and
(b)is not directly connected with or necessary to the management of that site,
must make an appropriate assessment of the implications of the plan or project for that site in view of that site’s conservation objectives.
(2) A person applying for any such consent, permission or other authorisation must provide such information as the competent authority may reasonably require for the purposes of the assessment or to enable it to determine whether an appropriate assessment is required.
(3) The competent authority must for the purposes of the assessment consult the appropriate nature conservation body and have regard to any representations made by that body within such reasonable time as the authority specifies.
(4) It must also, if it considers it appropriate, take the opinion of the general public, and if it does so, it must take such steps for that purpose as it considers appropriate.
(5) In the light of the conclusions of the assessment, and subject to regulation 64, the competent authority may agree to the plan or project only after having ascertained that it will not adversely affect the integrity of the European site or the European offshore marine site (as the case may be).
(6) In considering whether a plan or project will adversely affect the integrity of the site, the competent authority must have regard to the manner in which it is proposed to be carried out or to any conditions or restrictions subject to which it proposes that the consent, permission or other authorisation should be given.
(7) This regulation does not apply in relation to—
(a)a site which is a European site by reason of regulation 8(1)(c);
(b)a site which is a European offshore marine site by reason of regulation 18(c) of the Offshore Marine Conservation Regulations; or
(c)a plan or project to which any of the following apply—
(i)the Offshore Petroleum Activities (Conservation of Habitats) Regulations 2001(1) (in so far as this regulation is not disapplied by regulation 4 (plans or projects relating to offshore marine area or offshore marine installations) in relation to plans or projects to which those Regulations apply);
(ii)the Environmental Impact Assessment (Agriculture) (England) (No. 2) Regulations 2006(2);
(iii)the Environmental Impact Assessment (Agriculture) (Wales) Regulations 2017(3); or
(iv)the Merchant Shipping (Ship-to-Ship Transfers) Regulations 2010(4).
(8) Where a plan or project requires an appropriate assessment both under this regulation and under the Offshore Marine Conservation Regulations, the assessment required by this regulation need not identify those effects of the plan or project that are specifically attributable to that part of it that is to be carried out in the United Kingdom, provided that an assessment made for the purpose of this regulation and the Offshore Marine Conservation Regulations assesses the effects of the plan or project as a whole.
(9) In paragraph (1) the reference to the competent authority deciding to undertake a plan or project includes the competent authority deciding to vary any plan or project undertaken or to be undertaken.
S.I. 2001/1754, amended by S.I. 2007/77, 1842, 2010/1513, 2015/1431, 2016/529, 912, 1042 and 2017/582.
S.I. 2006/2522, amended by S.I. 2009/1307, 3264, 2010/1159, 2011/1043, 1824 and 2017/593.
S.I. 2010/1228, amended by S.I. 2011/974, 2183, 2012/742, 2013/755 (W. 90), 2014/3306 and 2015/664.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: