Review of existing decisions and consents
65.—(1) Where before the date on which a site becomes a European site or a European offshore marine site a competent authority has decided to undertake, or has given any consent, permission or other authorisation for, a plan or project to which regulation 63(1) would apply if it were to be reconsidered as of that date, the authority must, as soon as reasonably practicable—
(a)review its decision or, as the case may be, the consent, permission or other authorisation; and
(b)affirm, modify or revoke it.
(2) The authority must for that purpose make an appropriate assessment of the implications for the site in view of that site’s conservation objectives; and the provisions of regulation 63(2) to (4) and (8) apply, with the appropriate modifications, in relation to such a review.
(3) Subject to the provisions of Chapters 2 to 7, any review required by this regulation must be carried out under existing statutory procedures where such procedures exist, and if none exists, the appropriate authority may give directions as to the procedure to be followed.
(4) Nothing in this regulation affects anything done in pursuance of the decision, or the consent, permission or other authorisation, before the date mentioned in paragraph (1).