Modifications etc. (not altering text)
C1Pt. 6: power to amend conferred (24.1.2022) by Environment Act 2021 (c. 30), ss. 113, 147(3) (with s. 144); S.I. 2022/48, reg. 2(p)
C2Pt. 6 power to disapply or modify conferred (26.12.2023) by Energy Act 2023 (c. 52), ss. 293(4)(5), 334(3)(j) (with s. 293(6))
95.—(1) The revocation or variation pursuant to regulation 93(3), (4) or (5) of an authorisation under the Pipe-lines Act 1962 or a direction deeming planning permission to be granted takes effect upon the service of the notices required by regulation 94(1) or, where there is more than one such notice and those notices are served at different times, upon the service of the last such notice to be served.
(2) Where the competent authority decides not to proceed with the revocation or variation, the authorisation or direction has effect again as from the time of that decision, and thereafter has effect as if—
(a)any period specified in the authorisation or direction for the taking of any action, being a period which had not expired before the date on which the revocation or variation took effect, were extended by a period equal to that during which the revocation or variation had effect; and
(b)there were substituted for any date specified in the authorisation or direction as being a date by which any action should be taken (“the specified date”), not being a date falling before the date on which the revocation or variation took effect, such later date as postpones the specified date by a period equal to that during which the revocation or variation had effect.
(3) The revocation or variation of an authorisation or direction pursuant to regulation 93(3), (4) or (5) does not affect anything done under the authorisation or direction before the revocation or variation takes effect.