You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
There are currently no known outstanding effects for the The Conservation of Offshore Marine Habitats and Species Regulations 2017, Section 31.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
31.—(1) Where a competent authority in Scotland other than the Scottish Ministers proposes to agree to a plan or project under regulation 29 notwithstanding a negative assessment of the implications for a European site in Scotland or for a European offshore marine site in the Scottish offshore region—
(a)it must notify the Scottish Ministers; and
(b)it must not agree to the plan or project before the end of the period of 21 days beginning with the day notified to it by the Scottish Ministers as that on which the authority's notification was received by them, unless the Scottish Ministers authorise the authority to do so under paragraph (2)(b).
(2) In any case within paragraph (1), the Scottish Ministers may—
(a)at any time before the competent authority has agreed to the plan or project in question, give a direction to the competent authority prohibiting it from agreeing to the plan or project, either indefinitely or during such period as may be specified in the direction; or
(b)authorise the competent authority to agree to the plan or project subject to such conditions or restrictions as may be specified in the authorisation.
(3) The Scottish Ministers may amend or revoke a direction or authorisation under paragraph (2) at any time before the competent authority has agreed to the plan or project in question.
(4) Where a competent authority in Scotland agrees to a plan or project under regulation 29 notwithstanding a negative assessment of the implications for a European site in Scotland or for a European offshore marine site in the Scottish offshore region, it must notify the Secretary of State as soon as practicable following that agreement.
(5) Where the Scottish Ministers propose to agree to a plan or project under regulation 29 notwithstanding a negative assessment of the implications for a European site outside Scotland or a European offshore marine site outside the Scottish offshore region—
(a)they must notify the Secretary of State; and
(b)they may agree to the plan or project only after having been notified of the Secretary of State's agreement, which may be given subject to such conditions or restrictions as the Secretary of State may specify.
(6) Where a competent authority in Scotland other than the Scottish Ministers proposes to agree to a plan or project under regulation 29 notwithstanding a negative assessment of the implications for a European site outside Scotland or a European offshore marine site outside the Scottish offshore region—
(a)it must notify the Scottish Ministers and the Secretary of State; and
(b)it may agree to the plan or project only after having received notification from the Scottish Ministers that the Scottish Ministers and the Secretary of State have agreed that it may do so.
(7) In any case within paragraph (6), the Scottish Ministers may give a direction to the competent authority prohibiting it from agreeing to the plan or project, either indefinitely or during such period as may be specified in the direction, and may amend or revoke any such direction at any time before the competent authority has agreed to the plan or project in question.
(8) Any agreement between the Scottish Ministers and the Secretary of State that is the subject of a notification under paragraph (6)(b) may be subject to such conditions or restrictions as may be specified in the notification, and where the Scottish Ministers and the Secretary of State so agree, the Scottish Ministers may, at any time before the competent authority has agreed to the plan or project in question, amend or revoke a notification under paragraph (6)(b).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: