Agreement to plan or project: WalesU.K.
32.—(1) Where a competent authority in Wales other than the Welsh Ministers proposes to agree to a plan or project under regulation 29 notwithstanding a negative assessment of the implications for a European site in Wales or for a European offshore marine site in the Welsh offshore region—
(a)it must notify the Welsh Ministers; and
(b)it must not agree to the plan or project before the end of the period of 21 days beginning with the day notified to it by the Welsh Ministers as that on which the authority's notification was received by them, unless the Welsh Ministers authorise the authority to do so under paragraph (2)(b).
(2) In any case within paragraph (1), the Welsh Ministers may—
(a)at any time before the competent authority has agreed to the plan or project in question, give a direction to the competent authority prohibiting it from agreeing to the plan or project, either indefinitely or during such period as may be specified in the direction; or
(b)authorise the competent authority to agree to the plan or project subject to such conditions or restrictions as may be specified in the authorisation.
(3) The Welsh Ministers may amend or revoke a direction or authorisation under paragraph (2) at any time before the competent authority has agreed to the plan or project in question.
(4) Where a competent authority in Wales agrees to a plan or project under regulation 29 notwithstanding a negative assessment of the implications for a European site in Wales or for a European offshore marine site in the Welsh offshore region, it must notify the Secretary of State as soon as practicable following that agreement.
(5) Where the Welsh Ministers propose to agree to a plan or project under regulation 29 notwithstanding a negative assessment of the implications for a European site outside Wales or a European offshore marine site outside the Welsh offshore region—
(a)they must notify the Secretary of State; and
(b)they may agree to the plan or project only after having been notified of the Secretary of State's agreement, which may be given subject to such conditions or restrictions as the Secretary of State may specify.
(6) Where a competent authority in Wales other than the Welsh Ministers proposes to agree to a plan or project under regulation 29 notwithstanding a negative assessment of the implications for a European site outside Wales or a European offshore marine site outside the Welsh offshore region—
(a)it must notify the Welsh Ministers and the Secretary of State; and
(b)it may agree to the plan or project only after having received notification from the Welsh Ministers that the Welsh Ministers and the Secretary of State have agreed that it may do so.
(7) In any case within paragraph (6), the Welsh Ministers may give a direction to the competent authority prohibiting it from agreeing to the plan or project, either indefinitely or during such period as may be specified in the direction, and may amend or revoke any such direction at any time before the competent authority has agreed to the plan or project in question.
(8) Any agreement between the Welsh Ministers and the Secretary of State that is the subject of a notification under paragraph (6)(b) may be subject to such conditions or restrictions as may be specified in the notification, and where the Welsh Ministers and the Secretary of State so agree, the Welsh Ministers may, at any time before the competent authority has agreed to the plan or project in question, amend or revoke a notification under paragraph (6)(b).
Modifications etc. (not altering text)
C1Regs. 30-37 power to disapply or modify conferred (26.12.2023) by Energy Act 2023 (c. 52), ss. 293(4)(5), 334(3)(j) (with s. 293(6))