PART 2
.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
5. In this Part, “valid application” means an application that complies with the provisions of paragraphs 1 to 3.
6. The appropriate agency may, following receipt of a valid application, require the applicant to submit any further information or reports that it considers necessary to determine that application.
7.—(1) The appropriate agency must, by 30th June 2021, provide the applicant with the following information in relation to a valid application—
(a)whether a notice of the application has been or is to be published in accordance with section 37(1) M1;
(b)the date by which the applicant must be notified of the appropriate agency's decision on the application;
(c)the applicant's entitlement to appeal, in accordance with section 43(1)(b), against any failure by the appropriate agency to give notice, within the time period prescribed by paragraph 10(1), of its decision on the application.
(2) But if, when it receives the application, the appropriate agency serves a notice on the applicant under section 36A M2, and the applicant appeals against that notice, the appropriate agency must provide the information referred to in sub-paragraph (1) by 30th June 2021 or within 28 days of the final determination of that appeal, whichever is the later.
Marginal Citations
M1Section 37 was substituted by section 14(1) of the 2003 Act, and amended by S.I. 2013/755 (W. 90).
M2Section 36A was inserted by section 13(1) of the 2003 Act.
8.—(1) For the purposes of section 37(1), notice of an application must be published in at least one newspaper circulating in the locality of the proposed point of abstraction and on the appropriate agency's website.
(2) The notice must be published by—
(a)30th June 2021, or
(b)if there is an appeal under section 36A in relation to the application, within 28 days of the determination of that appeal or by 30th June 2021, whichever is the later.
(3) The notice must specify—
(a)the name of the applicant;
(b)the type of licence being applied for;
(c)the purpose of the abstraction;
(d)the point of abstraction;
(e)the period over which abstraction will take place;
(f)in the case of an application for a full licence, the quantity of water to be abstracted;
(g)where and when the application documents and the register containing details of the application may be inspected, and that such inspection is free of charge;
(h)the address to which any representations in relation to the application should be sent.
(4) The notice must not include any information that is to be excluded from a register by virtue of section 191A or 191B M3.
(5) The requirements of section 37(1) and (2) do not apply to any application if the appropriate authority notifies the appropriate agency that complying with those requirements in relation to that application would be contrary to the interests of national security.
(6) The requirements of section 37(1) and (2) may be dispensed with if it appears to the appropriate agency that the proposed abstraction would have no appreciable adverse effect on the environment.
Marginal Citations
M3Sections 191A and 191B were inserted by paragraph 170 of Schedule 22 to the 1995 Act and amended by S.I. 2013/755 (W. 90). Section 191B was amended by S.I. 2010/675.
9.—(1) This paragraph applies in the case of a valid application relating to abstraction in the area of a National Park or the Norfolk or Suffolk Broads.
(2) The appropriate agency must serve notice in writing of that application on the National Park authority for that Park or the Broads Authority, as the case may be, by 30th June 2021.
(3) The notice must include—
(a)a copy of the application;
(b)a statement that the National Park authority or the Broads Authority may make representations in writing to the appropriate agency in relation to the application within three months, beginning on the date on which the notice is served.
(4) The appropriate agency—
(a)must not decide on the application before the end of the three month period referred to in sub-paragraph (3)(b);
(b)must have regard to any representations made by the National Park authority or the Broads Authority when deciding on the application.
(5) This paragraph does not apply if the appropriate authority notifies the appropriate agency that giving such notice would be contrary to the interests of national security.
10.—(1) The appropriate agency must, by 31st December 2022, notify the applicant in writing of its decision on an application for a licence.
(2) If the appropriate agency grants a licence on terms that are different in any material respect from the application, or refuses an application, the notification must—
(a)include a statement of the appropriate agency's reasons for doing so;
(b)state the applicant's entitlement to appeal under section 43(1).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: