SCHEDULES

I1SCHEDULE 7LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Article 31

Annotations:
Commencement Information
I1

Sch. 7 in force at 22.12.2017, see art. 1

(1)

Location

(2)

Plot Reference Number shown on land plans

(3)

Purpose for which temporary possession may be taken

(4)

Relevant part of the authorised development

Land Plans - Sheet 1

Ashford

1/1/a

Upgrading existing road markings, traffic signals and signs.

Work No. 7

Ashford

1/1/b

Upgrading existing road markings, traffic signals and signs.

Work No. 7

Land Plans - Sheet 2

Ashford

2/1/c

Upgrading existing road markings, traffic signals and signs.

Work No. 7

Ashford

2/1/d

Upgrading existing road markings, traffic signals and signs.

Work No. 7

Ashford

2/1/e

Upgrading existing road markings, traffic signals and signs.

Work No. 7

Ashford

2/1/g

The strengthening of the existing Swatfield Bridge on the A20 Hythe Road. Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment, water pipeline and power cables.

Work Nos. 11, 16, 24, 25, 26, 27 and 28

Ashford

2/2/a

Use as a site compound area.

Work Nos. 1-29

Ashford

2/5/a

Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment and water pipeline.

Work Nos. 16, 24, 25

Ashford

2/5/aa

Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment and water pipeline.

Work Nos. 16, 24 and 25

Ashford

2/6/a

Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment and water pipeline.

Work Nos. 16, 24, 25

Ashford

2/6/aa

Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment and water pipeline.

Work Nos. 16, 24 and 25

Ashford

2/8/aa

Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment, water pipeline and power cables.

Work Nos. 16, 24, 25, 26, 27 and 28

Land Plans – Sheet 3

Ashford

3/14/c

Traffic sign amendments.

Work No. 9

Ashford

3/16/c

Use as a site compound area.

Work Nos. 1-29

Land Plans – Sheet 4

Mersham

4/1/b

Realignment of the A20 Hythe Road. Diversion works to telecoms equipment, water pipeline and power cables.

Work Nos. 17, 25, 26, 27 and 28

Mersham

4/1/bb

Re-alignment of the A20 Hythe Road.

Work No. 17

Mersham

4/1/g

Alteration work to the existing Kingsford Street. Diversion works to telecoms equipment and power cables.

Work Nos. 5, 24 and 28

Mersham

4/1/h

Alteration work to the existing A20 and installation of new traffic signs.

Work No. 17