xmlns:atom="http://www.w3.org/2005/Atom"
Article 31
(1) Location | (2) Plot Reference Number shown on land plans | (3) Purpose for which temporary possession may be taken | (4) Relevant part of the authorised development |
---|---|---|---|
Land Plans - Sheet 1 | |||
Ashford | 1/1/a | Upgrading existing road markings, traffic signals and signs. | Work No. 7 |
Ashford | 1/1/b | Upgrading existing road markings, traffic signals and signs. | Work No. 7 |
Land Plans - Sheet 2 | |||
Ashford | 2/1/c | Upgrading existing road markings, traffic signals and signs. | Work No. 7 |
Ashford | 2/1/d | Upgrading existing road markings, traffic signals and signs. | Work No. 7 |
Ashford | 2/1/e | Upgrading existing road markings, traffic signals and signs. | Work No. 7 |
Ashford | 2/1/g | The strengthening of the existing Swatfield Bridge on the A20 Hythe Road. Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment, water pipeline and power cables. | Work Nos. 11, 16, 24, 25, 26, 27 and 28 |
Ashford | 2/2/a | Use as a site compound area. | Work Nos. 1-29 |
Ashford | 2/5/a | Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment and water pipeline. | Work Nos. 16, 24, 25 |
Ashford | 2/5/aa | Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment and water pipeline. | Work Nos. 16, 24 and 25 |
Ashford | 2/6/a | Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment and water pipeline. | Work Nos. 16, 24, 25 |
Ashford | 2/6/aa | Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment and water pipeline. | Work Nos. 16, 24 and 25 |
Ashford | 2/8/aa | Upgrading existing lighting and installing new lighting. Diversion works to telecoms equipment, water pipeline and power cables. | Work Nos. 16, 24, 25, 26, 27 and 28 |
Land Plans – Sheet 3 | |||
Ashford | 3/14/c | Traffic sign amendments. | Work No. 9 |
Ashford | 3/16/c | Use as a site compound area. | Work Nos. 1-29 |
Land Plans – Sheet 4 | |||
Mersham | 4/1/b | Realignment of the A20 Hythe Road. Diversion works to telecoms equipment, water pipeline and power cables. | Work Nos. 17, 25, 26, 27 and 28 |
Mersham | 4/1/bb | Re-alignment of the A20 Hythe Road. | Work No. 17 |
Mersham | 4/1/g | Alteration work to the existing Kingsford Street. Diversion works to telecoms equipment and power cables. | Work Nos. 5, 24 and 28 |
Mersham | 4/1/h | Alteration work to the existing A20 and installation of new traffic signs. | Work No. 17 |