5.—(1) Subject to paragraph (3), in constructing or maintaining any of the scheduled works, the Agency may deviate—
(a)laterally from the lines or situations shown on the works plan to any extent within the limits of deviation; and
(b)vertically from the levels shown on the sections to any extent upwards or downwards.
(2) Without limiting the scope of paragraph (1), in constructing or maintaining the scheduled works the Agency may, within the limits mentioned in paragraph (1)—
(a)deviate from their points of commencement and termination as shown on the Order plans; and
(b)deviate from the design shown on the Order plans.
(3) The scheduled works must be constructed so that the unobstructed opening between the walls of the barrier, as shown on the Order plans, measures 25 metres wide.
(4) Nothing in paragraphs (3) or (4) of article 4 (power to construct and maintain works) authorises the Agency to execute any works in contravention of the restrictions imposed by paragraph (3).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: