The North London Heat and Power Generating Station Order 2017

Approval Process

17.  When submitting the plans to the statutory undertaker for approval under paragraph 8 or paragraph 9 the undertaker must send the plans to the statutory undertaker in hard copy by recorded post and by email to such address as the statutory undertaker may notify the undertaker in writing from time to time and clearly bearing the name of the project and contact details for responses, unless otherwise agreed with statutory undertaker.