24.—(1) No part of the authorised development shall be commenced until a control of radio emissions plan has been submitted to and approved in writing by the relevant planning authority, after consultation with the University of Manchester, (a Royal Charter corporation registered under number RC000797), of Oxford Road, Manchester, M13 9PL.
(2) The control of radio emissions plan must include a scheme to ensure that the authorised development operates at all times so the total radiated power emitted from the gas processing plant, Work No 14, does not exceed the following limits, integrated across the total bandwidths in Table 13 below.
Centre Frequency in MHz | Bandwidth in MHz | Limit from ITU-R 769 (Table 1) in dBW | Path loss in dB | Effective Isotropic Radiated Power in specified bandwidth in dBW |
---|---|---|---|---|
151.525 | 2.95 | -199 | 115.8 | -83.2 |
325.3 | 6.6 | -201 | 122.4 | -78.6 |
408.05 | 3.9 | -203 | 124.4 | -78.6 |
611 | 6 | -202 | 127.9 | -74.1 |
1413.5 | 27 | -205 | 135.2 | -69.8 |
1665 | 10 | -207 | 136.6 | -70.4 |
2695 | 10 | -207 | 140.8 | -66.2 |
4995 | 10 | -207 | 146.2 | -60.8 |
(3) The control of radio emissions plan shall also include the following—
(a)a scheme to establish and operate a liaison forum between the undertaker, the relevant planning authority and the University of Manchester, to meet at least annually to discuss and to seek, without prejudice to any enforcement powers held by the planning authority, the resolution of any issues raised by any party relating to the effect of radio emissions from the authorised development;
(b)a scheme to secure the testing of equipment and plant prior to the commencement of operations at the gas processing plant, Work No 14, so as to ensure compliance with sub-paragraph (2);
(c)a scheme to secure any mitigation measures which are required to ensure compliance with sub-paragraph (2); and
(d)a scheme to secure the monitoring of radio emissions to demonstrate compliance with sub-paragraph (2) during the normal operation of equipment and plant at the gas processing plant, Work No 14, including provision for reporting to the relevant planning authority and the University of Manchester on an annual basis and on reasonable request.
(4) The undertaker must—
(a)implement the control of radio emissions plan and associated schemes approved in accordance with sub-paragraphs (2) and (3); and
(b)ensure that the authorised development operates at all times in accordance with the limits in sub-paragraph (2).
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: