SCHEDULE 9PROTECTIVE PROVISIONS

PART 3FOR THE PROTECTION OF THE CANAL & RIVER TRUST

31.

(1)

The undertaker shall give to the engineer 30 days’ notice of its intention to commence the construction of any of the specified or protective works, or, in the case of repair carried out in an emergency, such notice as may be reasonably practicable so that, in particular, the Canal & River Trust may where appropriate arrange for the publication of notices bringing those works to the attention of users of the Canal & River Trust’s network.

(2)

The undertaker must–

(a)

at all times afford reasonable facilities to the engineer for access to a specified works during its construction; and

(b)

supply the engineer with all such information as he may reasonably require with regard to a specified work or the method of constructing it.