PART 8Unauthorised development
Interpretation34.
In this Part—
“enforcement functions” means—
(a)
the issuing of an enforcement notice under section 172 M1 of the Act (Issue of enforcement notice);
(b)
making an application for a planning enforcement order under section 171BA M2 of the Act (Time limits in cases involving concealment);
(c)
the issuing of a planning contravention notice under section 171C M3 of the Act (Power to require information about activities on land);
(d)
the issuing of a temporary stop notice under section 171E M4 of the Act (Temporary stop notice);
(e)
the issuing of a stop notice under section 183 M5 of the Act (Stop notices);
(f)
the service of a breach of condition notice under section 187A M6 of the Act (Enforcement of conditions); or
(g)
an application to the court for an injunction under section 187B M7 of the Act (Injunctions restraining breaches of planning control); and
“ground (a) appeal” has the meaning given in regulation 40; and
“unauthorised EIA development” means EIA development which is the subject of an enforcement notice under section 172 of the Act.