Regulations 5, 9 and 11

SCHEDULE 1E+WDevelopment requiring environmental impact assessment in any event

1.  Development to provide any of the following—E+W

(a)a nuclear generating station;

(b)a thermal generating station with a heat output of 300 megawatts or more;

(c)an electric line installed above ground with—

(i)a voltage of 220 kilovolts or more; and

(ii)a length of more than 15 kilometres.

2.  Development to provide a change to or extension of a generating station, or an electric line, of a description set out in paragraph 1 where the change or extension in itself meets the thresholds, if any, or description set out in that paragraph.E+W