The National Grid (Richborough Connection Project) Development Consent Order 2017

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Prior to the commencement of the works

8.  The licence holder must inform the MMO, the Environment Agency, GSDIG and the Sandwich Harbour Master in writing of the intended start date and the likely duration of licensed activities on a site at least 10 business days prior to the commencement of the first licensed activity.