2017 No. 820

Infrastructure Planning

The Keuper Underground Gas Storage Facility (Correction) Order 2017

Made

Coming into force

The Keuper Underground Gas Storage Facility Order 2017 (“the Order”)1, which granted development consent within the meaning of the Planning Act 2008 (“the Act”)2, contains correctable errors within the meaning of the Act3.

Before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 of the Act, the Secretary of State received a written request from the applicant4 for the correction of errors and omissions in the Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed Cheshire West and Chester Borough Council, the planning authority for the area in which the land to which the Order relates is situated, that the request has been received.

The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraphs 1(4) and (8) of Schedule 4 to, the Act, makes the following Order:

Citation and commencement1

This Order may be cited as the Keuper Underground Gas Storage Facility (Correction) Order 2017 and comes into force on 8th August 2017.

Corrections2

The corrections to be made to the Keuper Underground Gas Storage Facility Order 2017 are set out in the table in the Schedule to this Order, where—

a

column 1 sets out where the correction is to be made;

b

column 2 sets out how the correction is to be made; and

c

column 3 sets out the text to be substituted, inserted or omitted.

Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy

Giles ScottHead of Energy Infrastructure Planning and Coal LiabilitiesDepartment for Business, Energy and Industrial Strategy

SCHEDULE

Article 2

Where the correction is to be made

How the correction is to be made

Text to be substituted, inserted or omitted

Schedule 9, paragraph 57 definition of “specified work” sub paragraph (b)

After “may in any way adversely affect any apparatus”, omit

“the removal of which has not been required by the promoter under paragraph 62(2) or otherwise”

Schedule 9, paragraph 61(3)

For “paragraphs 64”, substitute

“paragraph 62”

EXPLANATORY NOTE

(This note is not part of the Order)

The Order corrects errors and omissions in the Keuper Underground Gas Storage Facility Order 2017, a development consent order under the Planning Act 2008, following a request under paragraph 1(5)(a) of Schedule 4 to that Act.