xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

SCHEDULE 10Deemed licence under the 2009 Act – generation assets (licence 1 – phase 1)

PART 2Conditions

Design parameters

5.—(1) In relation to a meteorological mast, each gravity base foundation must not have a diameter at the level of the seabed which is more than 20 metres.

(2) In relation to a meteorological mast, each suction caisson foundation must not have a diameter at the level of the seabed which is more than 15 metres.

(3) In relation to a meteorological mast, each jacket foundation must not have a footprint at the seabed which is more than 625 m2.

(4) In relation to a meteorological mast, each monopile foundation forming part of the authorised development must not have a diameter which is more than 8 metres.

(5) In relation to an accommodation platform, each gravity base foundation must not have a footprint of more than 15,855 m2.

(6) In relation to an accommodation platform, each jacket foundation must not have—

(a)a footprint at the seabed which is more than than 15,855 m2;

(b)more than one pile per leg or more than one suction caisson per leg.