Transitional provisions: no-scheme principle and compensation for disturbance4

1

The amendments made by section 32 and section 35 of the Act only apply in relation to a compulsory purchase of land which is authorised on or after 22nd September 2017.

2

For the purposes of this regulation, a compulsory purchase of land is authorised—

a

by a compulsory purchase order, on the day on which the order is—

i

confirmed by a Minister, the Welsh Ministers or another authority; or

ii

made by a Minister or the Welsh Ministers;

b

by an order under section 1 or 3 of the Transport and Works Act 19926, on the day on which the Secretary of State or the Welsh Ministers determine under section 13(1) of that Act to make the order;

c

by a harbour revision order, a harbour empowerment order or a harbour closure order under the Harbours Act 19647, on the day on which the order is made by a Minister, the Welsh Ministers or a person who is designated in an order made under section 42A8 of that Act;

d

by any other order, on the day on which the order is made by a Minister or the Welsh Ministers; or

e

by a special enactment, on the day on which the special enactment is enacted.