This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 12/10/2018.
Changes to legislation:
There are currently no known outstanding effects for the The Eggborough Gas Fired Generating Station Order 2018, SCHEDULE 10.
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Article 26
SCHEDULE 10E+WLAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
Table 11
(1) Number of plot shown on the land plans | (2) Purpose for which temporary possession may be taken |
---|
235, 330, 340, 345 | Temporary use required to facilitate construction of Work No. 4 |
370, 375, 425, 430, 495, 505, 535, 550, 580, 585, 590, 620, 625, 630, 635, 655, 660, 685, 690 | Temporary use as laydown, construction compound and construction use required to facilitate construction of Work No. 6 |
385, 390, 410, 415, 435, 440, 640, 645, 650 | Temporary use as laydown, construction compound, construction use and accesses required to facilitate construction of Work No.6 |
665, 670, 675, 680 | Temporary use as laydown, construction compound and construction use required to facilitate construction of Work Nos. 4 and 6 |
450, 455, 460, 465, 470, 480, 560, 565 | Temporary use to facilitate construction access to Work No. 6 |
615 | Temporary use as laydown, construction compound and construction use required to facilitate construction of Work No. 7 |