Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Article 26
SCHEDULE 10E+WLAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
Table 11
(1) Number of plot shown on the land plans | (2) Purpose for which temporary possession may be taken |
---|
235, 330, 340, 345 | Temporary use required to facilitate construction of Work No. 4 |
370, 375, 425, 430, 495, 505, 535, 550, 580, 585, 590, 620, 625, 630, 635, 655, 660, 685, 690 | Temporary use as laydown, construction compound and construction use required to facilitate construction of Work No. 6 |
385, 390, 410, 415, 435, 440, 640, 645, 650 | Temporary use as laydown, construction compound, construction use and accesses required to facilitate construction of Work No.6 |
665, 670, 675, 680 | Temporary use as laydown, construction compound and construction use required to facilitate construction of Work Nos. 4 and 6 |
450, 455, 460, 465, 470, 480, 560, 565 | Temporary use to facilitate construction access to Work No. 6 |
615 | Temporary use as laydown, construction compound and construction use required to facilitate construction of Work No. 7 |